Laserfiche WebLink
As shown below the total project cost is approximately $740,000 below the final estimate even when <br />including the relocation costs. Staff would also recommend that the contingency remain at 6% because <br />when compared to a street and utility project, this building construction is more complicated. <br /> <br />Recommendation: <br />Public Works and Oertel Architects, Inc. recommend that the City Council adopt the attached resolution <br />to accept the bids and award the contract for the construction of the Public Works Facility (City Project <br />No. 2017-C02). Additionally, staff recommends the approval of the following: <br />• Storage ‘pod’ rental from DART in the amount of $7,080 <br />• Temporary fencing installation by Century Fence in the amount of $5,515 <br />• Electrical work for relocation of the welder, air compressor, and security lighting by Muska <br />Electric in the amount of $7,795 <br />• SCADA relocation by AE2S in the amount of $14,400 <br /> <br />Respectfully submitted, <br /> <br /> <br />Brian Erickson – Public Works Director/City Engineer <br />Final Project <br />Estimate As Bid Difference <br />Design 247,000$ 247,000$ -$ <br />Construction <br /> Main Building 4,430,912$ <br /> Site Work 871,145$ <br /> Auxillary Structures 352,125$ <br /> Gen'l Conditions of Construction (5%)282,709$ <br /> Base Bid - Building 5,156,000$ <br /> Alternate 1 - Paint Vehicle Storage 21,910$ <br /> Alternate 2 - Concrete Material Storage 31,949$ <br /> Construction Subtotal 5,936,891$ 5,209,859$ (727,032)$ <br /> Construction Contingency (6%)339,251$ 312,592$ (26,659)$ <br />Construction Total 6,276,142$ 5,522,451$ (753,691)$ <br />Relocation Costs <br /> Storage Pods - 1 year rental 7,080$ <br /> Fencing 5,515$ <br /> Electrical - welder, air comp., lighting 7,795$ <br /> SCADA Relocation 14,400$ <br /> Hazardous Material Design 4,000$ <br /> Hazardous Material Abatement 4,000$ <br />Relocation Costs Total 42,790$ 42,790$ <br />Other Costs/Allowances 377,056$ 349,723$ (27,332)$ <br />Total Project Estimate 6,900,198$ 6,161,964$ (738,234)$ <br />TOTAL PROJECT ESTIMATE