Laserfiche WebLink
Ms. Pam Sheldon <br /> • March 3, 1997 <br /> Page 2 <br /> b. If construction involves dewatering in excess of 10,000 gallons per day or one <br /> million gallons per year, a DNR appropriations permit is needed. You are advised <br /> that it typicalltakes approximately 60 days to Pprocesshe permit application. <br /> c. If construction activities disturb five acres of land, or more, contractors are <br /> required to apply for a stormwater permit from the Minnesota Pollution Control <br /> Agency (Scott Thompson @ 296-7203). <br /> d. The comments in this letter address DNR-Division of Waters jurisdictional <br /> matters and concerns. These comments should not be construed as DNR support <br /> or lack thereof for a particular project. <br /> Sincerely, <br /> Molly Shodeen <br /> • Area Hydrologist <br /> MCS/cds <br /> c: Jim Ericson, City of Mounds View <br /> Wetland Files 62-171 and 62-258 <br /> • <br />