Laserfiche WebLink
4110 City of Mounds View <br /> CSAH 10 Corridor/Intersection Construction Improvement Cost Estimate <br /> Intersection Signal Cost Roadway Cost _ Misc. Cost Total <br /> County Road H 200,000 250,000 150,000 $600,000 <br /> Woodale Dr. --- --- 100,000 $100,000 <br /> County Road H2 200,000 1,000,000 300,000 $1,500,000 <br /> Edgewood Rd. --- 30,000 70,000 $100,000 <br /> Long Lake Rd. 200,000 30,000 70,000 $300,000 <br /> County Road I 200,000 800,000 200,000 $1,200,000 <br /> Silver Lake Rd. 200,000 30,000 70,000 $300,000 <br /> Groveland Rd. --- 50,000 25,000 $75,000 <br /> Spring Lake Rd. --- 50,000 25,000 $75,000 <br /> $4,250,000 <br /> CSAH 10 Corridor Trail Project Construction Cost Estimate <br /> Segment Length Lighting Cost Trail Cost Aesthetics Total <br /> Cost <br /> 1 1392 29,160 84,900 10,440 $124,500 <br /> 2 1541 31,940 94,000 11,560 $137,500 <br /> . 3 1261 26,120 <br /> 25,630 76,920 9,460 $112,500 <br /> 4 1217 74,240 9,130 $109,000 <br /> 5 1582 33,130 96,500 11,870 $141,500 <br /> 6 3630 76,300 221,400 27,300 $325,000 <br /> 7 1770 37,100 107,700 13,200 $158,000 <br /> 8 1780 37,200 108,500 13,300 $159,000 <br /> 9 1910 40,100 116,600 14,300 $171,000 <br /> 10 2110 44,500 128,700 15,800 $189,000 <br /> 11 2680 56,500 163,500 20,000 $240,000 <br /> $1,867,000 <br /> Gateway Sign Construction $150,000 <br /> Other Features $500,000 <br /> Engineering, Legal and Administrative Costs (35%) $2,368,450 <br /> Total $9,135,450 <br /> • Note:This estimate does not include any costs for right of way or easements <br /> that may be required due to roadway realignments or for temporary construction activities. <br />