Public Works Staff Report <br />3/3 <br />Trails/Sidewalk: <br />Hillview Road, Quincy Street and Jackson Drive (2016 Street and Utility Improvement Project – <br />Area I) <br />• Scope: Reconstruction of streets and utilities in the northeast quadrant of Mounds View. <br />Sidewalks will be constructed along Hillview, Jackson and Quincy. <br />• Budget: $4.2M (Street Improvement Fund). <br />• Construction is complete for the season. Most of the sidewalk has been constructed <br />except for tie in at Hillview and Quincy which will be completed in 2017. <br />• Contractor paved Terrace, Oakwood, and Hillview today. <br />• Estimated completion date week of July 10. <br /> <br />CSAH 10 Trail Segments #6 & #11: <br />• Scope: Construction of trail segments between Red Oak Drive and Groveland Road <br />(Segment #6) and between Woodale Drive and Edgewood Drive (Segment #11). <br />• Budget: $627,000 ($39,300 cost share with Ramsey County) (Street Improvement Fund). <br />• Construction underway. Northwest Asphalt has paved the trails, electrical sub has <br />completed light base and pole installation wiring is nearly complete. Curb cuts and <br />pavement repair at intersections is complete. Anticipate lighting completion in December <br />(dependent upon Xcel timelines). <br />• Contractor working to complete the electrical for trail lights. Tie in locations were changed <br />requiring additional wire and trenching <br />• Contractor is working on punch list items. <br /> <br />Greenfield Park: <br />RCWD ARJD#1 Project: Rice Creek Watershed District is planning the re-profiling and repair of <br />Anoka-Ramsey Judicial Ditch No. 1 which runs through Greenfield Park. Also included is Branch <br />No. 5 which is located behind the baseball outfield and crosses below the parking lot entrance. <br />Staff will be meeting with RCWSD to inquire the status of this work. <br />• RCWD has the goal of completing this project this year, but may wait until colder weather <br />for work to commence. <br />• Staff has been trying to get an updated timeline for the project from RCWD <br />• Staff meet with RCWD to clarify scope of work. Tree removals in along the ditch will likely <br />be required to allow equipment access. RCWD will need to coordinate the stabilization of <br />the bank after removals. Staff stated they will need to provide some cover near the <br />parking lot. No scheduled start date. <br /> <br />Other: <br />MCES Sewer Interceptor Project: Metropolitan Council Environmental Services is planning to <br />improve a large diameter sewer pipe at the northwest corner of Quincy and Hillview. MCES is <br />finalizing construction plans and have been reviewed by engineering division, comments returned <br />to MCES. MCES still planning on a 2015 project. Some trees have been tagged in order to be <br />transplanted in other City Parks. Project still scheduled to start later this spring. The work on the <br />meter station at the intersection of Quincy and Hillview has been delayed due to heavy rains and <br />flooding in September. Contractor is having to clean out the interceptor again due to heavy <br />sediment deposits in the line. Work will continue through the winter. A December closure of <br />Quincy Street to the north of Hillview is anticipated and is be required to complete Project is <br />nearly completed. Staff met with MCES to coordinate the installation of trail and planting of trees <br />as part of the restoration. A cooperative layout and tree location is being coordinated between <br />Mounds View and MCES. Working with MCES for final restoration of the southeast corner of the <br />park.