Laserfiche WebLink
2-�-e rmI: X-7 <br />IBMORANp[JM <br />Memo To :Mayor and City Council Members <br />From :Ric Minetor, Director of Public <br />works/City Engineer <br />Date :December 6, 1989 ` <br />subject :County Road I - Supplemental Agreement <br />Contractor Delay due to Right -of -Way Negotiations <br />Ramsey County is in the process of finaling this project. The <br />last remaining item of contention is the contractor's claim for <br />damages due to delays to the project schedule caused by right-df- <br />way negotiations. The attached supplemental agreement authorizes <br />the payment of this claim on a lump sum basis. The claim amount <br />is for $15,656.82 as noted on the attached letter from <br />Progressive Contractors Incorporated. The County has determined <br />that this is a valid claim under the provisions of the <br />specifications. <br />I have reviewed this matter and recommend approval and <br />authorization for the Mayor to sign the supplemental agreement on <br />the behalf of the City. <br />M <br />