The proposed schedule <br />for the project is as follows: <br />April 1987 <br />County Board approval to proceed with <br />contracts with the Bonding T <br />consultants, and architect, and <br />conceptual approval of the overall <br />plans. <br />April/May 19B7 <br />Library staff Building Program <br />Committee writes program <br />May/June 1987 <br />Library Board/Library Director and <br />architect consider possible sites, <br />apply site selection criteria, and <br />prioritize sites <br />June 1987 <br />Library Board considers building program <br />June 1987 <br />Library Board requests County Board to <br />sell bonds <br />July 1997 <br />Library Board requests County Board to <br />acquire selected site <br />May -Oct. 1987 <br />Architect designs library, prepares bid <br />specifications; project bid <br />Oct. 1987-June 1988 <br />Construction <br />July 1988 <br />Library opens <br />OR <br />4 <br />