HomeMy WebLinkAboutgr00090_000004_pg094-005Member Christensen introduced the following resolution
and moved its adoption:
RESOLUTIONPRLC61VIUG CONSTRUCTION BIDS;
AWARDING A CONTRACT FOR CONSTRUCTION OF WATER WORKS
IMPROVEMENT NO. 1960 - DETERMINING THE TOTAL COST
OF WATER WORKS IMPROVEMENTS NO. 1960 - 1, 2 and 3
AND CALLING FOR THE SALE OF BONDS.
BE IT RESOLVED By the Village Council of the Village of
Mounds View, Minnesota as follows:
(1) That it is hereby found, determined and declared that
the lowest two bids submitted by responsible contractors for the
construction of the respective schedules of work of Water Works Improve-
ment No. 1960 - 3 are as follows:
BIDDER SCHEDULE PRICE
Herbst Construction Co.
Minneapolis, Minnesota $199,393.00
Austin P. Keller
St. Paul, Minnesota $203,880.30
(2) That the contracts for the construction of Water Works
Improvement No. 1960 - 3 are hereby awarded to the lowest bidder for
each respective schedule of work; and the Clerk is hereby authorized
and directed to return the bid deposits of all bidders except the
lowest two bidders of each schedule of work. The bid deposits of the
lowest two bidders of each respective schedule shall be retained pending
the execution of contracts.
(3) The Mayor and Clerk are hereby authorized to enter into
contracts with the low bidder for each schedule of work upon said bidder
furnishing a satisfactory corporate surety bond conditioned upon the
satisfactory performance of the work according to plans and specifications
and otherwise as required by law.
-2-