Mr. Sullivan also gave a report on the joint meeting :v1'-hh09
the New Brighton Village Council regarding a joint Municipal Court.
Another meeting will be held after further information is assimilated
by the two Village Attorneys.
The Attorney and Fiscal Agent reported on the bids for the
Bond Sale. The low bidder was First National Bank of St. Paul and
they recommended the Council accept that bid. Motion by Sullivan
to concur with Attorney and Fiscal Agents recommendation and award
the sale of 130,000 Bonds to low bidder, First,National Bank of St.
Paul at an interest rate of 3.4587% and a total interest cost of $31,475.00
Seconded by Malvin. 4 Ayes.
The checks of the unsuccessfW bidders will be returned through
the Clerkts Office.
Mr. and Mrs. Richardson - 8443 *Red Oak Drive requested a delay
in the water hook -up because water table in their area is too high to
dig in the line.
Motion by Malvin to delay the late hook -up fee cut -off date
for 8443 Red Oak Drive because of high water table, until water table
is lowered enough to make excavation without flooding.
Seconded by Sullivan! 4 Ayes.
Clerkts Office was instructed to attach a note regarding this
action to permit application.
Mr. Skiba reported that N.S.P. was installing a power r pole
on the proposed right of way of County Road H at Highway # 10.
The Engineer was instructed to investigate the possibility*
of water service hook -up to an isolated home on Edgewood Drive,
across from the Junior High School.
The Engineer reported the following regarding Judicial Ditch # 1:
1. State Aid Money is available and can be used for this purpose in
connection with Hillview Project.
2. Approximate cost would be from $250.00 to $500.00
3. The Contractor has done some clearing on his own.
Motion by Malvin to clean Judicial Ditch # 1 from the (approx.)
corner of Quincy Street to Highway # 8 at an estimated cost of $250.00
to $500.00. Work to be performed under a change order on Hillview Road
Project, prepared by the Engineer. Funds to come from Municipal State
Aid. Seconded by Hodges. 4 Ayes.
The Attorney read a letter regarding this ditch and gave a
report on his meeting with the County Board of Commissioners.
He stated that the Village would get little or no assistance
from the County and the only other alternatives were to undertake the
cleaning on our own, or take it to the Court that created it and ask
for a ruling on who pays for the cleaning.
The Acting Mayor opened the Public Hearing for Mr. C.W. Peterson
on rezoning.
The Clerk read the legal description and the published and
mailed notices required.
Mr. Bell, Attorney for the applicant, told of the projected
plans for the plot of ground. The owner will have a building constructed
and lease it to a concern or operate on his own a dairy store, or sporting
goods store or an auto accessory store.
The Acting Mayor called three times for objections to the
rezoning and there were none.