Loading...
HomeMy WebLinkAboutgr00090_000011_pg06-007surface drainage, building a sanitary sewer system and re- building and resurfacing existing roads. Mr. Les Knutsen, Village Engineer, proceeded with a review of the technical data. He explained the maps on display illustrating the various phases of this construction. Soil samples were taken within the area and analyzed, and these were on display for those who wished to check them. He stated the Council had directed them to make an investigation in January of 1959. Illustrations by map showed the main interceptor system and the various collection points, and the proposed super high- way as it is now laid out for the area. He stated that construction will have to be modified for the right -of -way the Minnesota High- way Department will take at that time. There will be no loss to the Village by any highway changes, should they occur. The third map showed the proposed drainage system and gave an explanation of the original requests for such a system to correct existing deficiencies in the Village. It is a system of ditches and conduit which will drain present low areas in the Village of surface waters. He stated the second real benefit, at the time of sanitary sewer construction, is tht it would pro- vide an outlet for the discharge of well- pointing water. A question was raised asking why this water could not be discharged through the sanitary sewer system. Mr. Knutsen stated that it could be done for the present, but it would require -6-