HomeMy WebLinkAboutgr00090_000023_pg070- 3 -
SCHEDULE D
500,000 GALLON ELEVATED WATER TANK
LUMP SUM BID ALTERNATE PROPOSAL
.JHOLDER BID SURETY BASE PROPOSAL DEDUCT REMARKS
rittsburgh -Des Moines Steel Co. 5% Bid Bond $163,000.00 No Bid #1 Add.
1015 Tuttle Street
Des Moines, Iowa 50308
Chicago Bridge & Iron Co.
332 South Michigan Avenue
Chicago, Illinois 60604
* Universal Tank & Iron Works
Rural Route 8, Box 360
Indianapolis, Indiana 46231
5% Bid Bond $158,830.00
5% Bid Bond $147,890.00
No Bid #1 Add.
$151,875.00 * #1 Add.
* Bidder altered proposal form and inserted a lump sum bid on the alternate proposal.
SCHEDULE F
TWO PUMP HOUSES
PLANHOLDER BID SURETY LUMP SUM BID REMARKS
* Petersen - Templin, Inc. 5% Bid Bond $101,113.00 #1 & #2 Add.
Crystal, Minn.
Orvedahl Construction Inc. 5% Bid Bond $112,900.00 #1 Add.
- -1.1 Country Club Drive
leapolis, Minnesota 55427
_..eberg Construction 5% Bid Bond $109,443.00 #1 & #2 Add.
3092 North Rice Street
St. Paul, Minn. 55113
DeDolph Construction Co. 57 Bid Bond $122,000.00 #1 & #2 Add.
771 West 7th Street
St. Paul, Minnesota 55102
Dupre Construction Company 5% Bid Bond $123,000.00 #1 & #2 Add.
535 East Cottage
St. Paul, Minnesota 55101
SCHEDULE G
TWO WATER TREATMENT PLANTS & APPURTENANCES
PLANHOLDER
* Petersen - Templin, Inc,
Crystal, Minnesota
Acton Construction
Route 1 - Box 256A
Hugo, Minnesota 55038
,enberg Construction
1 Marshall Avenue
. Paul, Minnesota 55104
BID SURETY LUMP SUM BID REMARKS
5% Bid Bond $302,777.00 #1 & #2 Add.
5% Bid Bond $312,218.00 #1 & #2 Add.
5% Bid Bond $324,600.00
#1 & #2 Add.
210 Days