HomeMy WebLinkAboutgr00090_000025_pg076- 3 -
MSP (Blanchard/Hodges) To defer the assessments on various parts of 1969 -3,
1970 -1 and 1970 -3 for A. Spitzer, Lot 1 Block 2 Greenfield Addition totaling
$1,476,72, F. Visger, Lot 5 Block 2 Greenfield Addition totaling $3,783.41,
J. Capitz, S 110' of Lot 11 Block 2 Greenfield Addition totaling $3,476.82,
R. Gale, 59- 0410 - 040 -67 totaling $2,025.63 subject to their signing deferred
assessment agreements and the filing thereof. 4 Ayes
MSP (Hodges /Neisen) To authorize the payment of the street assessment on
Mounds View park parcel 59- 0410 - 040 -68 in the amount of $2,904.99 for Project
1970 -1 and 1970 -3 from the construction fund. 4 Ayes
Councilman Hodges' Report
Councilman Hodges reported that the Brauer basic park plan would be ready in
October.
Engineer BoVhm's Report
Engineer Boehm reported that the repair of Well #1 was taking more time than
anticipated.
In addition, he expected the final estimate for 1968 -3 Schedule C to be ready
for the next meeting.
Engineer Boehm reported that the water tower is being painted.
MEP (Blanchard/Hodges) To adjourn at 8:52 P.M. 4 Ayes
spectfully Submitted,
f
tc tcc .7 ---1. C ,Zi-Cti
Dennis S. Zyllf J
Clerk- Administrator