Engineer Boehm's Report
Engineer Boehm reported on a sewer problem at Woodcrest and Long Lake Road. It
appears that a riser has settled into the pipe which is 28 feet deep.
MSP (Rustad /Blanchard) To authorize American Pipe Services to inspect and
repair the damaged pipe.
Inspector Skiba is to check the cost of having Clark and Moores do some digging
at the break on behalf of the Village, rather than tying up our crew for assistance
in the repair.
MSP (Rustad /Hodges) To accept the final plans and specifications for Sanitary
Sewer and Water Projects 1971 -1 and 1971 -la.
MSP (Blanchard /Hodges) To set the bid date for Sanitary Sewer and Water Projects
1971 -1 and 1971 -la for June 21st at 12 noon.
MSP (Neisen /Rustad) To adjourn at 10:02 P.M.
Respectfully Submitted,
Dennis S. Zylla,
Clerk- Administrator