to pay the cost of a lawsuit.
Councilman Baumgartner declared that Inspector Skiba was in error by not getting
in writing Birkeland's commitment to correct the drainage problem.
Motion (Pickar) To accept the Engineer's report and to proceed with the project
as scheduled. Motion died for lack of second.
Councilman Johnson suggested that either Birkeland puts the pipe in and pays for
it or the Village puts it in and assesses it.
MSP (Neisen- Hodges) To table the matter until October 23, 1973 at 8:30 P.M.
giving Attorney Meyers time to talk to Mr. Birkeland relating the Council's concern
for the matter and explaining to him that the Council feels the cost of the
improvement, whether it's installed by him or the Village, should be borne by Mr.
Birkeland. And that the Village will consider legal action against Mr. Birkeland
if the total cost of the improvement is not paid by him. 5 Ayes
MSP (Neisen- Johnson) To continue the hearing on October 23, 1973 at 8:30 P.M.
Meeting temporarily adjourned at 10:08 P.M.
Mayor Neisen called the regular meeting back to order.
5 Ayes
Mayor Neisen's Report
Mayor Neisen announced that filings for office closed today and Councilman Johnson
will be running unopposed for Councilman and he will be running unopposed for Mayor.
Mayor Neisen read the Police Report for September.
Clerk - Administrator Zylla's Report
MSP (Hodges - Baumgartner) To approve the licenses: General Contractor - Marvin's
Roofing, Russell Scott Construction; Heating - Mill City Heating & A.C. Co., Twin
City Furnace Co.
MSP (Johnson- Hodges) To approve the bills: General Fund checks #7743 through
#7796, Payroll Account checks #1047 through #1049, Payroll checks #575 through
#599. Transfer check #7794 transferring $31.74 to the Payroll Account from the
General Account to correct transfer made in error on 7- 23 -73, and check #7795
transferring $10,065.38 to Payroll Acount to pay gross pay of October 15, 1973.
From General - $7,911.74, from Water - $1,368.92, from Sewer - $784.72. Total
disbursements of $27,275.95.
5 Ayes
5 Ayes
MSP (Johnson- Hodges) To approve the installation of two or three street lights
along County Road H in the vicinity of the Malvin, Pettibone, and Herbst offices. 5 Ayes
The Clerk was directed to send a letter to NSP requesting prompt installation of
the street lights in Red Oak Estates.
MSP (Pickar - Hodges) To adopt Resolution No. 613 declaring certain lands non
conservation and requesting certain land previously forfeited be conveyed to the
Village of Mounds View.
5 Ayes