August 11, 1975
Councilman Baumgartner's Report
Councilman Baumgartner announced that the Park and Recreation Commission
would be meeting August 14, 1975 at 6:30 p.m.
Councilman Hodges' Report
Councilman Hodges commented on a problem a resident is having with sod
int the Project 1973 -4 area (8406 Red Oak Drive). He referred this to
the engineer for follow up.
Councilman Pickar's Report
Councilman Pickar reported that the Lakeside Park Commission would
be meeting Thursday, August 14, at 8:00 p.m., at the Spring Lake
Park City Hall.
Mayor Johnson's Report
Mayor Johnson announced that this Wednesday, August 13, 1975, at
8:00 p.m. the official meeting of the Planning Commission would be
held for presentation of the comprehensive plan.
A resolution is to be approved by the Planning Commission for adoption
of the plan on August 27, 1975. The Plan will then be sent to the
Metropolitan Council for their review and comments and it will be
then be presented to Council for formal adoption as recommended by
Planning Commission.
After the plan has been adopted, no public land or capital improvement
shall be made until it has been certified and filed with the City. The
City must submit in writing to the Planning Commission to be sure all
changes tie in with the comprehensive plan.
Attorney Meyers will check the procedural aspects of the comprehensive
plan.
Councilman Baumgartner would like to get together with the Planning
Commission to review the plan.
Engineer Comstock's Report
Engineer Comstock read a letter from Engineer Bearden recommending
that City approve specifications as submitted for the water main to
serve Perkins Cake & Steak.
MSP (Baumgartner - Pickar) to approve plans and specifications for the
entire water main and sewer construction of Ervin Herbst property as
prepared by Toltz, King, Duvall, Anderson and Assoc., Inc.
Administrator Achen reported on specifications to improve the ditch
in front of Mounds View Square shopping center. He received a letter
last Thursday from Paster Enterprises saying they didn't want to wait
for the City to do the work. They were going to do it themselves.
Administrator Achen responded to their letter saying that is what the
City wanted them to do all along and requested they do it according to
the specifications. Mr. Paster has been working on the ditch and as
it is now graded it may not be easily maintained because of the steepness
of the grade.
4 Ayes