HomeMy WebLinkAboutgr000990_000040_pg136-2-
MSP (Hodges - Baumgartner) to approve the Clara Ford Addition
as recommended by the Planning Commission referred to as
Exhibit A.
Mayor Johnson adjourned the public hearing and called the
regular Council meeting back to order.
Attorney Gerald Frisch, 2350 W. Seventh St., St. Paul, repre-
senting Mounds View Square Shopping Center, asked permission
for the proceedings to be transcribed by a court reporter.
Mayor Johnson replied that it is not the policy of the Council
to allow tape recording devices in the Council Chambers. Such
devices are deemed to be disruptive to the Council's delibera-
tions. The Council has a recording secretary, and the minutes
are available to all parties interested. Mr. Frisch stated
that he proposed to have a court reporter present or he would
object to being heard on it. The Mayor told him that they
would not allow a court report to be present. Mr. Frisch
stated that they would not appear in this regard then -- they
will take it by deposition. He wanted his objection noted
in the minutes.
4 ayes
Mayor Johnson recessed the regular meeting and called to order
at 8:30 p.m. the public hearing on Public Improvement Project
1975 -4A. Admin. Achen stated that this improvement began
last year as a result of the floods on the property around
Mounds View Square Shopping Center. To solve the immediate
drainage problem in that area, an emergency improvement under
authority of MN Statutes 429 was begun. The ditch was recon-
structed and the culverts were lowered in the driveway accesses
and under Long Lake Rd. Ramsey County did some ditch recon-
struction work on County Rd. I also. The owners realigned
their roof so the water flowed off the east side of the building.
Some asphalt berming was put around the culvert at the Co. Rd. I
access. The project was not completed because of the early
snow last year.
The property owner originally stated that he would do the
project, but then requested that the city do the job.
Driveways still have to be resurfaced and the ditch banks
stabilized to prevent erosion. This spring the city engineer
evaluated what had to be done, but the construction company
who was to do it went bankrupt. The Council called for this
public hearing, for specifications to be prepared, and bids to
be received. The city has received an informal report from
Banister and Short regarding the proposed comprehensive storm
water management plan. They want to drain this property
northwest rather than southeast, using a storm sewer line.
Their recommendation was to not encase the ditch unless the
highway department absolutely requires it. At such time as
the storm sewer line is installed, it may be possible to remove
the holding ponds that are at the shopping center now. The
staff and the city engineer recommend that the project be
reduced in scope to the extent of eliminating the piping. This
was discussed with the highway department, which tentatively
agrees.