HomeMy WebLinkAboutgr00090_000041_pg216July 26, 1976 Page 5
Councilman Baumgartner questioned the starting date for the
project. Eng. Hubbard indicated the contractor would be given
10 days to execute an agreement and after that 30 days to
complete the project. Eng. Hubbard also stated that this
project will be assessed against the property owner. Atty.
Meyers stated it will be assessed under Chapter 429 subject to
the rights of appeal and contest.
MS (Hodges- Shelquist) to accept the lowest bid of Central
Landscaping, Inc. in the amount of $11,654.50.
Councilman Pickar suggested adding the type of pipe to be used.
Councilman Shelquist stated the State's recommendation had
been reinforced concrete.
MSP (Shelquist- Hodges) to amend the motion to stipulate that
reinforced concrete piping be used. 3 ayes
1 nay
Councilman Baumgartner asked the engineer what his recommenda-
tion is on the type of pipe. Eng. Hubbard stated he understood
the theory behind bidding was the concern that the sand be kept
from building up. No matter which pipe you put in, you are
going to have the problem. There is no difference in price for
either pipe.
Councilman Shelquist stated the concrete is a more permanent
structure. This is the City's opportunity to provide something
more permanent and it isn't going to cost us one cent to do it.
Vote on the main motion as amended. 4 ayes
IMPROVEMENT PROJECT 1976 -1. Eng. Hubbard stated two bids were
received for the sealcoating project. Low bid was Allied Black-
top for $43,915.20. Bituminous Roadways submitted a bid for
$48,021.30. Engineer's estimate was $39,625. 1976 estimated
budgeted amount was $29,500. Based on this, Eng. Hubbard
recommended rejecting all bids and combine this year's and next
year's program. In the meantime, City forces can do some of
the repair work and some may be done on force account. Combining
the two years' program would make it possible to put out bids
earlier in the year, thus picking up more and possibly better
bids with the pricing being on more units. Administrator
Achen reinforced the Engineer's recommendation and explained
that Eng. Hubbard having been recently hired by the City was
not involved in the original planning of this bid.
Admin. Achen also stated that we should develop a sealcoating
program that is practical. City adopted this program on assump-
tion of $30- 35,000, now we are talking about $40,000 in second
year of project. The program should be reevaluated to determine
if it wouldn't be better to stretch the work over seven years
and make it more financially sound. Even at the $30,000 level,
City is operating $10,000 in the hole. Admin. Achen again
recommended rejecting all bids until next year, giving our new
Engineer time to reevaluate the sealcoating program and try to
reduce costs.