HomeMy WebLinkAboutgr00090_000044_pg107-5-
PUBLIC HEARING - ON -SALE INTOXICATING LIQUOR LICENSE - JOSEPH HARTINGER, DBA
LAUNCHING PAD SUPPER CLUB
Mayor Pickar reported that a letter had been received from the Launching Pad shortly
before the meeting began, in which they stated that they would like, to postpone the
hearing for the on -sale license for the Launching Pad as it appeared there would be
a new owner for the Launching Pad, shortly, and that the new owner would then apply
for the license.
PLANS AND SPECIFICATIONS FOR BONA ROAD EXTENSION
Engineer Hubbard presented that plans and specifications for the Bona Road extension,
Project 1977 -2, which were prepared by Banister -Short and reported that a problem
with the storm sewer had been discovered just that afternoon which would require more
study. The problem was that the storm sewers presently in existence are believed to
be already over capacity and that a new development would burden them even more. The
potential problem would be that during heavy rains, the water could back up and go over
the tops of the curbs. However, Engineer Hubbard and Banister -Short felt the problem
could be solved by putting drainage through between the property lines and running it
through the back, where it would eventually meet up with the storm sewer on County
Road H2.
Administrator Achen asked what was meant by "over capacity ". Engineer Hubbard replied
that Banister -Short had done an analysis of the existing pipes. The existing piping
is 27" wide and would not be adequate to meet future needs of a new development.
Councilmember Baumgartner asked if the developer of the property was aware of the
problem, and Engineer Hubbard replied that he was not, as the problem had just been
discovered that afternoon.
Councilmember Ziebarth expressed concern with holding the development up for another
three weeks, until the next Council meeting, at which time the problem could hopefully
be solved.
Administrator Achen clarified the situation by explaining the pro's and con's, that the
Banister -Short study indicated the pipe was inadequate; however, they did not know the
capacity of the pipe at the present time, and that it was an odds game. Banister -Short
would not agree to come to the Council Meeting and state definitely that the problem
could be solved by going through the property lines,
John Riggs, developer of the property, expressed his displeasure at the nei,r delay and
reminded the Council that he had turned in the grading plans for the area over a month
ago and felt that t he problems should h a�.. ve been iL cA-=-. out in the Planning _:
.w... v> _ ,
and asked the Council what they wanted him to do next.
Engineer Hubbard stated that the grading plan should be reworked and easements would
be required. Mr. Riggs replied that the easements had already been planned for in
the plat.
Administrator Achen suggested that the Council could make a motion, with conditional
approval, and that they wold have a second chance to work out the problem, when the
bids were submitted for approval, and that if the builder did not meet the specifi-
cations, it could be turned down at that time.
Councilmember Ziebarth asked what the next step would be for the City Engineer. Engineer.
Hubbard replied that he would determine if an overflow ditch would solve the problem
and that if the grades would have to be changed, he would go the builder with that
information.