ITEM G. Approve the September 11, 1978, bills for payment.
ITEM H. Approve the following licenses:
BOWLING ALLEY - new, expires 12/31/78
Mermaid
2200 Highway 10
CONTRACTORS ® expire 6/30/79
General - new
R. H. Romers Construction
1605 Excelsior Ave.
Floodmaster Engineering Corp.
1545 Selby Ave.
Page 6
General R renewal
Professional Roofing Service
7257 Yucca Lane
Future Fence
1409 - 105th Ave< N.E.
IMPROVEMENT PROJECT 1978 -3 CONSTRUCTION CONTRACT
Dan Boxrud of Short - Elliott- Hendrickson stated that ten bids were received on the
project, which ranged in price from $776,291.90 to $1,024,000.00, with the low bid
being received from Barbarossa & Sons. He stated that the low bid was $52,597 under
the estimate of $821,838 and recommended that Council award the project to the low
bidder.
•
MSP (Pickar- Hodges) to accept the bid of Barbarossa & Sons, with a base bid of
$776,291.90. 4 ayes
Councilmember Baumgartner asked if the Wooddale option should also be approved.
MSP (Pickar - Ziebarth) to amend the previous motion to accept the Wooddale option
of $2949.00. 4 ayes
IMPROVEMENT PROJECT 1978 -4 CONSTRUCTION CONTRACT
Mr. Boxrud stated that the low bid on Project 1978 -4, of Barbarossa & Sons is $29,778
over the estimated cost of $118,450 made by the City Engineer last July. He stated
that several factors were involved, such as the small size of the project, the require-
ment that it be completed in 1978, and soil conditions.
Attorney Meyers stated that it would be advisable to readvertise for bids since the
bids received exceeded the engineer's estimate by such a great percentage.
Mr. Boxrud stated he did not believe they would get much better bids, and pointed out
that the first three bids were very close. Administrator Achen added that the speci-
fications should be changed enough to warrant the rebidding and recommended that the
project competion date be extended to 1979. He added that any additional cost to
rebid would have to be borne by those being assessed. If the property owners are
willing to guarantee payment of assessment, these bids could be accepted.
Attorney Meyers stated that if the affected owners execute waivers stating they do not
object to the overrun, the project could be ordered. Mr. Boxrud added that he felt
the project could be completed in 60 days, which would not present a problem for this
construction season.