HomeMy WebLinkAboutAgenda Packets - 2005/10/03 (2)
CITY OF MOUNDS VIEW
CITY COUNCIL WORK SESSION AGENDA
MOUNDS VIEW CITY HALL
Monday, October 3, 2005
7:00 p.m.
ROLL CALL: Marty, Stigney, Gunn, Flaherty, Thomas
PUBLIC COMMENT
Citizens may speak to issues not on tonight’s agenda. Before speaking, please give your full
name and address for the minutes. Also, please limit your comments to three minutes.
Agenda Items Discussed by Consensus
_______ 1. Presentations
A. Mounds View School District in regard to future planning
and decisions by the school district
B. Association of Metropolitan Municipalities (AMM) Presentation (Louis
Jambois)
C. Park Building Discussion
1. Groveland Recommendations
2. Random/Clubhouse Recommendations
_______ 2. Citizen Communication
A. City Hall Message Board – Continue operations? (verbal report)
________ 3. Development and Planning
A. Review Medtronic Development Stage Plans for their CRM Campus
Project
B. Initial Allocation of Land Proceeds
_______ 4. Review//Discuss Effective Council Meetings Articles
Next Council Work Session: Monday, November 7, 2005 (New Brighton City Hall)
Next City Council Meeting: Monday, October 10, 2005 (New Brighton City Hall)
Item No. 1C
Meeting Date: October 3, 2005
Type of Business: WK
WK: Work Session; PH: Public Hearing;
CA: Consent Agenda; CB: Council Business
City Administrator Review _______
City of Mounds View Staff Report
To: Honorable Mayor and City Council
From: Greg Lee, Director of Public Works
Item Title/Subject: Park Building Review and Recommendations
GROVELAND PARK BUILDING
Background:
Bids for the Groveland Park Building Replacement Project were received on
Thursday, July 14, 2005 at City Hall. The bids were composed of the base bid to
perform the construction of the building and a bid alternate for the air conditioning
of the building.
A total of two (2) bids were received for this project. The low bid of $289,700.00
was submitted by Unicorp, Incorporated of Saint Paul Minnesota. The bid
alternate for air conditioning was $7,000.00.
A complete bid summary follows:
BIDDER’S NAME BASE BID BID ALTERNATE
Unicorp, Incorporated $289,700 $7,000
Meisinger Construction $302,000 $5,500
The engineer's estimate was $227,000 -- 27.6% less than the lowest actual bid.
On July 25, 2005, the bids were presented to the City Council. It was
recommended that, should the City Council wish to proceed with this project, the
City should utilize the construction services of TKDA to oversee the project and
ensure that the contractor adheres to the plans and specifications. TKDA had
submitted a letter of agreement in the amount of $14,000.00 to provide these
services.
Based on the bids received and the estimated construction services, the
following estimated total project cost summary was presented on July 25, 2005:
TKDA Plan Preparation $19,600
Construction $289,700
AC – bid alt. $7,000
TKDA construction services $14,000
TOTAL ESTIMATED COST $330,300.00
As per resolution 6558, Sixty-five percent (65%) of the total project cost would be
financed utilizing Park Dedication Funds (Account No. 285-4470-3030), and the
remaining 35% would be derived for the Special Project Funds (Account No. 280-
4180-7050).
$214,695 - 65% financed by Park Dedication Fund
$115,605 - 35% financed by Special Project Fund
At the July 25, 2005 City Council Meeting, the City Council rejected the bids
citing that the project was too expensive and asked the Parks, Recreation, and
Forestry Commission to look at alternatives.
Discussion:
On July 28, 2005 the Parks, Recreation, and Forestry Commission began
discussing and exploring alternatives for the replacement of the Groveland Park
building. Discussions and investigation have continued over the past several
months. The following is a brief summary of several options were explored:
Public Works crews to do the demolition
The Public Works crews could do demolition if necessary. However, this may not
represent that great of a savings. Having limited labor resources may also be an
issue. The demolition would most likely occur in late winter/early spring. This is
when other, perhaps more critical, activities such as spring park duties, street
repair, street sweeping, and boulevard repairs occur.
Review Bid Items
The Commission requested a list of line items associated with this project from
the low bidder. Unicorp, Incorporated submitted a list they used to develop their
bid. This list is attached for the City Council’s review. There were no items that
were easily identifiable that could be reduced or eliminated to save costs.
Identify Fixed Costs
The Commission was concerned as to how the project was presented to the City
Council on July 25, 2005. A list of all project related costs was presented. These
costs totaled $330,300. The Commission suggested that a more equitable way to
view the cost is to identify fixed costs and remove them from consideration –
essentially identifying the increased cost from the “do nothing option” to replacing
the Groveland Building.
Two such costs that were identified were the demolition costs and plan and
specification costs. These costs have been or will be incurred, regardless of what
option is selected. Since the City will need to remove the Groveland building at
some point in time regardless of whether it is replaced - should the demolition
costs be removed from the overall costs?
The demolition cost is estimated to be $8,000 to $10,000 and the cost to develop
the plan and specifications amount of $19,600 has already been expended.
Need to look at what items are needed
The Commission went through an exhaustive review of the proposed building to
see if there were items that could be eliminated in an effort to reduce the overall
cost of the building.
The restrooms were discussed. The question was raised -- ”Is a restroom
needed?“ Lambert does not have a restroom. However, it is also not being used
to any great extent. When looking at shrinking /eliminating amenities in this
building, the Commission also looked at the impact of the usefulness of the
building. The Commission recommended that the building continue to retain
restrooms.
The question of whether the building should be heated was raised. With the
recommendation to retain the rest rooms, it was also unanimously recommended
to heat the building.
The Commission looked at the need to have two restrooms. Could one unisex
restroom be created? This is a possibility. The plan would be to simply not
include the fixtures and retain the second bathroom as storage. To eliminate the
room would require a redesign of the building plans. The Commission discussed
that it could be included as a bid alternate. However, it should be pointed out that
the removal of a toilet and sink may not be that great of an overall cost savings.
Reducing the building’s overall square footage was reviewed. This is a fairly
basic space. It was suggested by the Commission that the proposed building
retain the space as planned to be used for its current functions. It was also stated
that this is a public building – not private. Because of this, there are additional
requirements such as restroom floor space that need to be compliant with the
Americans with Disabilities Act (ADA). The Commission recommended
unanimously to maintain the planned floor space.
There is double door to the mechanical room. Is there a need for this second
door and is there a savings to reduce to one door? It was determined that the
opening could be reduced to require one door. However, it was also determined
that it is beneficial to retain the double doors and that the reduction to a single
door does not represent a cost savings due to the additional cost of material
needed to fill in where the second door would be.
The firm of TKDA was contacted to get their recommendations for reducing
costs. TKDA stated that this is a very basic building and that there are no real
“extras” on it. When asked if lower quality materials could be used, TKDA stated
that the materials specified are the “middle of the road” and they would not
recommend lesser material in a public building.
There was a consensus from the Committee not to change the plans and lose
any amenities in the building at this time. The Commission felt that this is a very
basic building without any unnecessary amenities but would still serve the public.
A comparison was made to New Brighton’s buildings, which have fireplaces,
knotty pine walls and ceiling, dividers, very nice restrooms, etc.
Masonry construction versus “stick construction”
The Commission asked, “Would TKDA need to start over with plans and specs
with a stick building?” It was determined that TKDA would not need to start over
since there are many shared design construction features of the two. However,
how much re-work of the plans is needed to develop a stick design is uncertain at
this time.
The line item bid list that was submitted by Unicorp, Incorporated showed the
Concrete/Masonry line item to be $59,800. This cost would include a concrete
floor, which would also be specified in a stick building construction. Also,
considering that wood material would need to be added to the bid list, there
doesn’t appear to be that great of a savings for substituting stick construction
over masonry. Given the minimal cost difference, the overall durability, the
increased longevity and maintenance reduction cost, the Commission
recommended that masonry construction be considerer.
As a note, the existing Golf Course Clubhouse was constructed in 1995. It is a
“stick” constructed building with a total square footage of 1380 sq. ft. The total
cost to construct Golf Course Clubhouse including construction, inspection, and
engineering was $231,657.98 in 1995. The ENR Construction Cost Index from
July 1995 was 5484. As of July 25, 2005, the ENR CCI is 7422. Therefore, to
convert a project cost from July 1995 to July 2005, the 1995 cost should be
multiplied by 1.3534. Doing this the current estimated cost to construct the Golf
Course Clubhouse is $313,525.91
Groveland Clubhouse
Total Cost $330,300 $313,525.91
Square Footage 1217 1380
Cost per sq. ft. $271.41 $227.19
Construction options: Volunteers
The Commission looked into whether high schools, trade schools, vocational
schools or colleges would be capable of building the Groveland Park Building. It
appears that it is possible. A great deal of coordination would be needed. There
was also the issue - can this be done legally? The City's legal counsel and the
City's insurance agent were contacted. In summary, the City could allow a
volunteer group to construct a park building with few legal or insurance issues
involved. The main problem would be that if a volunteer group were to be
covered under the City's insurance policy, the City would need to supervise the
project. Given this, and the fact that the material cost would remain the same,
there probably would be little advantage to this option.
Other options - Prefab construction
This is an option. However, the issues of maintenance costs, durability, and
longevity exist.
Bidding / Contract Options
There are three possible bid revision options:
1.) Revise the plan – this was reviewed and discussed by the Commission.
There are little recommended changes other than perhaps having a single
bathroom as a bid alternate (and keep the AC unit as a bid alternate).
2.) Increase the construction timeframe by revising the specifications to allow
for construction any time during the 2006 construction season. This option
was also recommended by TKDA
3.) Increase the number of potential bidders – develop an information
campaign and target smaller bidders who typically do not use the
Construction Bulletin to know of potential projects and those contactors
who do not typically bid on government projects.
Commission Recommendation
A motion was made to direct Staff to bring this issue back to the City Council with
a summary of the options that were reviewed, discussed, and investigated by the
Commission; also, to present the Commissioner’s recommendation to re-bid this
project in an effort to obtain more favorable bids. This would done by changing
the specifications to give the contractor the entire 2006 construction season to
complete the project – have a December 1, 2006 substantial completion date.
There would also be an advertisement campaign to reach the smaller contractors
who typically do not bid on public contracts. The bid would also include a bid
alternate for the air conditioning unit it be installed.
RANDOM PARK BUILDING / GOLF COURSE CLUBHOUSE
Background:
In 2002, the City’s Capital Improvement Program (CIP) indicated that the
Random Park Building was scheduled for replacement in 2006. However, due to
budget restraints this project was later moved back in the CIP schedule to the
year 2013.
Discussion:
With the closing of the Golf Course, the City has been investigating the feasibility
of moving the Golf Course Clubhouse to a new site within the City. There are
two feasible relocation sites for the clubhouse: Groveland Park and Random
Park. The Parks, Recreation, and Forestry Commission have been discussing
and exploring these two sites.
Assuming that both the existing Groveland and Random Park buildings were in
the same condition and were both scheduled for replacement at this time, the
Random Park building would make a much better choice for replacement with the
Golf Course Clubhouse.
The Random Park building is used exclusively for classroom style and similar
type activities. Conversely, the Groveland Park building is used for social
gatherings during the spring and summer months and as a warming house in the
winter. A stick constructed building, such as the Golf Course Clubhouse, would
be subjected to far greater wear and abuse at the Groveland site versus the
Random site. This would certainly affect its longevity.
The City has received four (4) quotes to move the clubhouse. They ranged from
$28,500 to $96,000. The quotes did not include tree trimming, power lines work,
or intersection help/removal. These would be additional costs. Moving expenses
for the clubhouse may be Tax Increment Financing (TIF) eligible. The City’s
Economic Development Coordinator will continue to look into this possibility.
There would also be costs associated with the setup of the Clubhouse on a new
site. These include: removal of any existing building ($8,000 - Groveland or
Random), utility work ($5,000), foundation construction ($52,000), removal and
replacement of interior surfaces ($50,000). The total estimated cost could be
around $115,000. Total project including moving the building is estimated to be
$150,000.
The Commissioners had questions regarding the doors (entry and interior) of the
Golf Course Clubhouse. The interior doors are hollow wood doors and would be
susceptible to damage – especially in a warming house setting with ice skates.
The Commissioners were concerned that the clubhouse is not a park building
type of structure.
There are three general options regarding the fate of the clubhouse:
1.) The clubhouse is demolished by Medtronic – no expense to the City.
2.) Remove the clubhouse and relocate it somewhere within the City – the
Commissioners should provide recommendation as to the preferred
site and identify any associated issues.
3.) Remove the clubhouse and sell it– is there a salvage value?
Commission Recommendation
After exhaustive study of the options pertaining to the fate of the Golf Course
Clubhouse, and detailed evaluation of park needs at Random Park versus
Groveland Park, the Park and Recreation and Forestry Commission voted
unanimously to recommend that, should the City retain the clubhouse, that it be
relocated to Random Park. Furthermore, there was a consensus of the
Commission that should the Random Park site be selected as the preferred
relocation site of clubhouse, a neighborhood meeting should be conducted
to present the proposal to the community and allow them the opportunity to
provide comments before final City Council resolution.
It was discussed and concluded that it would not be economically feasible to
move the existing Random Building to Groveland Park.
Recommendation:
Parks and Recreation and Forestry Commission, along with Staff, is looking for
direction on this matter. Specifically, the Commission is looking for Council input
on re-bidding the Groveland Park Building Replacement Project and input on the
fate of the Golf Course Clubhouse.
Respectfully Submitted,
Greg Lee, Director of Public Works