HomeMy WebLinkAboutResolution 7243RESOLUTION 7243
CITY OF MOUNDS VIEW
COUNTY OF RAMSEY
STATE OF MINNESOTA
ORDERING THE 2009-2010 STREET AND UTILITY IMPROVEMENT
PROJECT AND AUTHORIZING THE PREPARATION OF PLANS AND
SPECIFICATIONS
WHEREAS, on December 11, 2006 the City Council held a public hearing
and approved Resolution 6982 approving the Feasibility Report for the 2007-
2008 Street and Utility Improvement Project; and
WHEREAS, the proposed 2009-2010 Street and Utility Improvement
Project will be the same project as the proposed 2007-2008 Street and Utility
Improvement Project, with the addition of Red Oak Drive north of Sherwood
Road; and
WHEREAS, it is recommended that the City proceed with the 2009-2010
Street and Utility Improvement Project based on the feasibility report for the
2007-2008 Street and Utility Improvement Project and developed based on the
Street and Utility Improvement Program adopted on October 22, 2007; and
WHEREAS, should the Council wish to proceed with this project, the next
step in the public improvement process is to order the project; and
WHEREAS, should the Council wish to proceed, the next step in the
engineering process is to order the preparation of construction plans and
specifications; and
WHEREAS, the installation of water quality and storm water runoff
reduction devices such as raingardens may require additional temporary
construction easements and permanent easements; and
WHEREAS, the financing for this project is proposed to be derived from a
combination of several sources, including, but not limited to: the City of Mounds
View Utility Franchise Fee, Municipal State Aid (MSA), Tax Increment Financing,
and general city wide tax levy.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
Mounds View, Ramsey County, Minnesota as follows:
Said improvements are hereby ordered and shall hereafter be
known and referred to as the 2009-2010 Street and Utility
Improvement Project.
2. Said ordering of the improvements shall be valid until March 24,
2009 - a period of one year from the date of the Public Hearing.
3. That the preparation of the construction plans and specifications for
the 2009-2010 Street and Utility Improvement Project is hereby
authorized.
4. The cost of said improvements shall be funded by a combination of
several sources, including, but not limited to: the City of Mounds
View Utility Franchise Fee, Municipal State Aid (MSA), Tax
Increment Financing, and general city wide tax levy.
5. All activities associated with the preparation of temporary
construction easements and permanent easement agreements are
hereby authorized. These activities may include discussions with
property owners, necessary appraisals, boundary sketches, legal
descriptions, and drafting the legal easement documents.
Adopted this 24'h day of March 2008.
,~
Rob Marty, Mayor
(ATTEST)
James Ericson, Interim City Administrator
(SEAL)
Infrastructure Improvement Program
2009 - 2010 Street and Utility Improvement Project
Action Plan and Schedule
Prepared March 14, 2008
Revised /Update: XXXXX XX, 2008
May 22, 2006 City Council authorized preparation of as feasibility report for the 2007-
2008 Street and Utility Improvement Project
December 11, 2006 City Council approved the feasibility report for the 2007-2008 Street and
Utility Improvement Project
January 31, 2007 Strom Water Enhancement Meeting -introduced proposed raingarden
plan for the 2007-2008 Street and Utility Improvement Project
February 12, 2007 City Council accepted a petition in opposition to the proposed 2007-2008
Street and Utility Improvement Project
August 13, 2007 City Council authorized preparation of an updated feasibility report for the
2008 Street and Utility Improvement Project
August 30, 2007 Public Information Meeting on the 2008 Street and Utility Improvement
Project
September 10, 2007 Work on the 2008 Street and Utility Improvement Project is terminated
October 8, 2007 The City Council made a motion to authorize Staff to initiate preparation
of a 2009-2010 Street and Utility Improvement Project by working with the
engineering consultant to collect data, mainly on Red Oak Drive north of
Sherwood Drive, and to initiate the development of a raingarden program.
October 22, 2007 The City Council adopted the Street and Utility Improvement Program.
March 10, 2008 City Council sets a Public Hearing Date for the 2009-2010 Street and
Utility Improvement Project
March 12, 2008 Public Hearing notice published on City's web site
COMPLETED
PLANNED
March 19, 2008 Public Hearing notice published in official newspaper
March 24, 2008 Public Hearing, order project, authorize preparation of plans and
specifications
April 21, 2008 Streets and Utilities Committee discusses 1) General Design issues, and
2) Raingarden Program- homework assignment: review January 31,
2007 raingarden meeting and February 5, 2007 Work Session Meeting
May 5, 2008 General Design Issues and Raingarden Program discussed with City
Council -homework assignment: Council to review January 31, 2007
raingarden meeting and February 5, 2007 Work Session Meeting
May 19, 2008 Hold neighborhood meetings: General Design Issues: pedestrian corridor
(Red Oak Drive and Hillview Road), Hillview Park parking lot,
Hillview/Fairchild access, mailbox grouping...
June 16, 2008 Streets and Utilities Committee discusses Raingarden Program
July 7, 2008 Raingarden Program (Draft) introduced to City Council
July 21, 2008 General Design Issues -Committee holds second neighborhood
meetings: finalize citizen input and Committee recommendation
July 28, 2008 City Council approves Raingarden Program
August 4, 2008 General Design Issues with Committee recommendation discussed with
City Council
August 11, 2008 City Council provides final direction on General Design Issues
August 18, 2008 Raingardens in the 2009-2010 Street Project -Committee holds second
neighborhood meetings: finalize citizen input and Committee
recommendation
September 2, 2008 Raingardens in the 2009-2010 Street Project is discussed with City
Council, citizen input presented
September 8, 2008 City Council provides final direction on Raingardens in the 2009-2010
Street Project
September 8, 2008 Start 2010 Street and Utility Improvement Project
November 24, 2008 City Council Approves Plans and Specifications, sets a bid date, and
authorizes the advertisement for bids
December 31, 2008 Permits from Other Agencies
January 22, 2009 Bids Received (Thursday 10:00 AM, Mounds View City Hall)
February 9, 2009 Award Construction Contract
March 26, 2009 Neighborhood Preconstruction Meeting held
May 4, 2009 Construction Begins (Phase 1)
September 14, 2009 Start 2011 Street and Utility Improvement Project
November, 2009 Construction Completed (Phase 1)
May 3, 2010 Construction Begins (Phase 2)
July /August, 2010 Placement of Bituminous Wear Surface (Phase 1) - Optional'
September 13, 2010 Start 2012 Street and Utility Improvement Project
October, 2010 Construction Completed (Phase 2)
July /August, 2011 Placement of Bituminous Wear Surface (Phase 2) - Optional*
* -The City may allow the bituminous wear surface to be placed during the calendar year that
the based course is placed, provided several conditions are met. These conditions pertain to the
amount and depth of excavation that occurred under the streets, the ambient air temperature at
the time of paving, and actual mixture temperature at the time of paving.