HomeMy WebLinkAboutGroveland Park Building Replacement - Project SchedulePrepared: December 14, 2005
Groveland Park Building Replacement Schedule
Authorized plans and specifications May 10, 2004
Letter of Agreement submitted by TKDA June 21, 2004
Letter of agreement rejected June 28, 2004
Authorized Request For Proposal (RFP) July 12, 2004
Authorized the publication of a Request For Proposal (RFP) August 23, 2004
Approved Letter Agreement with TKDA October 25, 2004
Authorized plans and specifications October 25, 2004
Approved Plans and Specifications June 13, 2005
Set a Public Improvement Hearing Date June 13, 2005
Ordered the Project June 13, 2005
Set a Bid Date June 13, 2005
Authorized to Advertise for Bids June 13, 2005
Bids Opened July 14, 2005
Bids Rejected July 25, 2005
--------------------------------------------------------------------------------------------------
Set New Bid Date January 9, 2006
Send bid advertisement to local paper / construction bulletin January 13, 2006
Send Bid Information to Local Contractors January 18, 2006
First Advertisement for bids January 18, 2006
Second Advertisement for bids January 25, 2006
Bid opening February 21, 2006
Award contract February 27, 2006
Contractor able to start March 6, 2006
Specified Completion Date December 1, 2006