City of Mounds View
Memo
To: Parks and Recreation Commissioners
From: Greg Lee
CC: Steve Dazenski
Shannon Roepke
Date: 12/19/2002
Re: Skate Park at the Community Center
At the November 21, 2002 Parks and Recreation Meeting, the Commissioners changed their recommended Skate Park site location from Groveland Park to the Community Center. The Commissioners
also made a motion to have staff identify costs associated with constructing a Skate Park at the Community Center.
--------------------------------------------------------------------------------------------------------------------------------------------
The following is a cost summary of items that would be associated with construction of constructing a Skate Park at the Community Center.
RECONSTRUCT THE SURFACE THE BASKETBALL COURT - $20,000
The existing court slopes 6” in 34 feet – this would not be conducive to skate boarding or any other wheeled sport
* If Public Works removes the existing bituminous $18,000
FENCING $4,500
Place a 10 foot cyclone fence around the Skate Park – three sides (105’X34’X34”)
IRRIGATION ALTERATIONS $1,500
The existing irrigation would need to be altered: relocate, raise sprinkler heads,
change valveing.
LIGHTING $2,000
Add two additional lights to the roof of the Community Center. One light may need
to be mounted on a pole located further away from the building so as to illuminate
the entire Skate Park.
ENTRANCE DOOR $8,000
To provide an entrance to the Skate Park area from the Community Center,
an additional exterior security door would need to be constructed. This would
need to be done in such a fashion so as to preserve or provide a new fire exit door.
SECURITY CAMERA $1,000
Add two exterior cameras and run wire
LANDSCAPE REMOVAL / REPLACEMENT $800
Remove existing shrubs and trees re-sod any disturbed area
SIGNAGE $400
Signs stating the rules and operation of the skate park
TRASH RECEPTACLES $720
Provide two heavy-duty trash receptacles
BENCHES $1,800
Provide three heavy-duty benches
RESTROOMS AND DRINKING FOUNTAIN $0
Assume users of the Skate Park will utilize the facilities inside the Community Center
TOTAL INFRASTRUCTURE IMPROVEMENTS $38,720
The total 2003 budget for the Stake Park is $55,000. Therefore, there would only be $16,280 remaining to purchase equipment. Adding tax, the City’s buying power is further reduced to
$15,280
Infrastructure Improvements $38,720
Skating Equipment $14,710
Tax $ 956
TOTAL $54,386
Attached is a graphic from Skatewave showing a layout costing $14,710.
FOR COMPARISON PURPOSES THE SAME EXERCISE WAS PERFORMED FOR THE GROVELAND SITE:
RESURFACE THE TENNIS COURT (fill cracks and paint) $1,500
SIGNAGE $400
TRASH RECEPTACLES $720
BENCHES $1,800
BUILD PATHWAY TO RESTROOMS AND DRINKING FOUNTAIN $700 TOTAL $5,120
Infrastructure Improvements $ 5,120
Skating Equipment $46,620
Tax $ 3,030
TOTAL $54,770
Attached is a graphic from Skatewave showing a layout costing $46,620.
--------------------------------------------------------------------------------------------------------------------------------------------
ESTIMATED ANNUAL SUPERVISION COSTS
The following is a financial analysis of the cost to provide supervision for the Skate Park at the Community Center.
ASSUMPTIONS:
Wages for person providing supervision - $7.50 per hour
Skate Park is open: 2:00 p.m. to 10:00 p.m. Monday through Friday during school months
8:00 a.m. to 10:00 p.m. Weekends during school months
8:00 a.m. to 10:00 p.m. Everyday during non-school months
When the YMCA has the Community Center open for other activities, only one person is needed to supervise the skate park. When the YMCA does not have the Community Center open, two people
will be needed to supervise the skate park (for safety reasons: one at the front desk / one observing skating activities)
The Community Center is open:
9:00 a.m. to 10:00 p.m. Monday through Friday during school months
8:00 a.m. to 9:00 p.m. Saturday during school months
11:00 a.m. to 6:00 p.m. Sunday during school months
9:00 a.m. to 7:00 p.m. Monday through Friday in June, July, and August
9:00 a.m. to 5:00 p.m. Saturdays in June, July, and August
Closed Sundays in June, July, and August
ESTIMATED ANNUAL SUPERVISION COSTS:
During school months (April, May, September)
M-F 40 hours, Sat. 15 hours, Sun. 21 hours = 76 man hours per week
76 man hours per week X 14 weeks = 1064 man hours
1064 man hours X $7.50 per hour = $7,980
June, July, and August
M-F 90 hours, Sat. 20 hours, Sun. 28 hours = 138 man hours per week
138 man hours per week X 13 weeks = 1794 man hours
1794 man hours X $7.50 per hour = $13,455
Total Estimated Annual Supervision Cost
$7,980 + $13,455 = $21,435
IT WILL TAKE AN ESTIMATED $21,500 TO SUPERVISE THE SKATE PARK
-------------------------------------------------------------------------------------------------------------------
POINTS OF CONSIDERATION
Looking at the big picture: This skate park was to be a trial project. The goal was to invest minimally in infrastructure improvements and evaluate the skate parks success or failure
at the end of 2003.
With the Groveland site, if is the project is a success, there is room for expansion. If it is a failure, the City can sell the state ramps at a very little over all loss to the City.
The tennis courts could be reinstated for a very minimal cost.
With the Community Center site, nearly $40,000 will need to be invested in the site preparation. If the project is a success, there is no room for expansion on this already small site.
If it is a failure, the City will have wasted $40,000 in addition to the cost to convert the park back to basketball courts.
Should a skate park be a success, the Groveland site allows for expansion. If it continues to grow in popularity, the City would always have the option to develop a larger regional skate
park by purchasing the site to the south of the Community Center or developing a site with in the City Hall / Public Works complex.
Reports from Public Works, Parks Division, and Police indicate that the basketball courts behind the Community Center are being used far more frequently and by far more people than the
tennis courts at Groveland Park. The YMCA has confirmed that the basketball courts adjacent to the Community Center are used extensively.
The Banquet Center has voiced a concern that a skate park may have a negative image for potential clients the City is trying to rent the facility to (Attached is a memorandum dated November
21, 2002 from Dabney Bradley – Banquet Facility Manager). The Center is also concerned for the personal property of visiting guests utilizing the Banquet Facility.
Even with supervision and monitoring, there is a possibility graffiti on the Community Center will become an issue.
The roof of the Community Center is 12 to 14 feet high. Installing a 10-foot fence that adjoins to the Community Center will provide an access to the roof for juveniles.
Addressing the concern of placing a skate park in a neighborhood area: There are four dwelling units that are adjacent to the Groveland Park tennis courts. There are 12 adjacent to the
basketball courts behind the Community Center.
Is it a realistic assumption that patrons of the skate park will take off their inline skates upon arriving at the Community Center, walk 70 feet through the center, and put them back
on again? Then to repeat this every time they need to use the restroom or get a drink of water.
Are there any other cities in the metro area, state, or the country that charges for a Tier I skate park?