Laserfiche WebLink
' RCM 10408.01 <br /> ' PROJECT SCHEDULE <br /> The following schedule is proposed for the 1998 street and watermain improvements. The schedule may be <br /> revised at a later date to reflect any unforeseen changes. <br /> Submit feasibility report August 12, 1997 <br /> City ouncil authorize 1 <br /> ty spans and specifications August 12, 1997 <br /> Hold neighborhood meetings with affected property owners October 21, 1997 <br /> City Council approves plans and specifications and authorizes <br /> ' advertisement for bids October 28,1997 <br /> Receive bids and compute final assessments December 16, 1997 <br /> City Council approves 3 resolutions on improvement hearing <br /> and special assessments December 23, 1997 <br /> ' Hold public hearing for project and assessments,award bid, <br /> and call for bond sales February 1998 <br /> Award sale of bonds March 1998 <br /> Begin construction May 1998 <br /> Substantial completion of construction August 1998 <br /> Certify assessments to County Auditor August 1998 <br /> ' Final completion of construction July 1999 <br /> CONCLUSION AND RECOMMENDATION <br /> The total estimated project cost is$770,000. This project is feasible from a technical perspective and should not <br /> present major difficulties during construction. The existing street pavements and watermains show extensive <br /> 1 deterioration, and any method of rehabilitation short of reconstruction is not cost-effective; therefore it is <br /> recommended the streets be reconstructed and watermain be replaced. The City of St. Anthony and affected <br /> ' property owners will make the final decision as to the feasibility of this project. <br /> 12 <br />