1 <br /> 7. FEASIBILITY AND RECOMMENDATION <br /> ' Project costs are anticipated to be approximately$2,200,000,which includes the total <br /> street and utility reconstruction of Wilson Street,Harding Street, and 32nd Avenue NE. . <br /> ' Due to the inadequate capacity of the sanitary sewer mains and the storm mains, this <br /> project is both feasible and necessary from an engineering standpoint. The installation of <br /> the sanitary and storm sewer will require the removal of the existing street and the <br /> ' removal and exposure of the existing water distribution lines. Under these conditions it is <br /> both"feasible and necessary to replace the existing street and water main. Furthermore, <br /> due to the location and condition of the existing utilities, the available street right-of-way, <br /> ' the existing soils conditions, and the need to provide utility service to all of the properties <br /> in the project area, other methods of improving the utility systems and the roadway are <br /> not feasible or cost effective. <br /> 1 <br /> Based on our analysis and data presented, the proposed project is feasible, necessary and <br /> cost effective from an engineering standpoint. We recommend the reconstruction of the <br /> sanitary sewer, water main, storm sewer and streets as detailed this report. <br /> 1 <br /> 1 <br /> ' City of St.Anthony-2002 Street and Utility Improvement Project . <br /> Feasibility Report <br /> WSB Project No. 1065-592 Page 9 <br />