My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
CC PACKET 08231994
StAnthony
>
City Council
>
City Council Packets
>
1994
>
CC PACKET 08231994
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
12/30/2015 6:21:57 PM
Creation date
12/30/2015 6:21:46 PM
Metadata
Fields
SP Box #
22
SP Folder Name
CC PACKETS 1994-1998
SP Name
CC PACKET 08231994
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
90
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
STOP N GO WORKPLAN FOR CORRECTIVE ACTION, DRILLING SERVICES AND TANK REMOVALS. <br /> 1 Month 7 <br /> ID Name Scheduled Start Scheduled Finish Week 1 WA,-k 2 Week 3 Week 4 Week 5 Week 6 Week 7 <br /> 1 REVIEW OF PAST SITE ACTIVITIES 6/19/94 8:00am 6/24/94 5:00pm <br /> ..............---.................-. ................ <br /> 2 <br /> ------...................... ........................................................................................................ ............ ............................ <br />............. <br /> 3 Review the MPCA working file 6/24/94 5:00pm 7/19/94 9:12am <br /> ................................................ ......................................... <br /> 4 Review past and current environmen 6/27/94 5:00pm 7/19/94 9:12am <br /> .............. ................... ............................................................................. <br /> 5 Review past request by the MPCA 6/28/94 5:00pm 7/19/94 12:00pm <br /> ............. ........................... ............. ........... ........................ ............. .............................................. <br /> ................I..._.._.........-........ <br /> '6 Complie information for Petrofund 6/29/94 5:00pm 7/19/94 12:00pm <br /> .............................................................. ............. <br /> 7 <br /> ....................... ...................................... ............. .............. ..... .... ........................ .......__.......__......_....I._..._.._._.. <br /> 8 WORKPLAN PRESENTATION 7/19/94 8:00am 7/19/94 5:00pm <br /> ..................................... ............. <br /> 9 Complete and issue collective work. 7/19/94 8:00am 7/19/94 5:00pm <br /> ........................................................................... .. ........ <br /> 10 Coordinate workplan with city boar 7/21/94 8:00am 8/1/94 12:00pm <br /> .......... .............. ...... <br /> 11 Apply for and recieve proper permi 8/8/94 8:00am 8/15/94 5:00pm <br /> ............ <br /> 12 Schedule approved subcontractors 8/15/94 5:00pm 8/16/94 12:00pm <br /> ..................................... ............ ................ ...... -------------------------- <br /> 13 <br /> ...................... <br /> 14 SCHEDULED DRILLING SERVICES 8/15/94 5:00pm 8/17/94 12:00pm <br /> ............................. ....................................................................... ............... ............................ .................... <br /> 15 Utility check for on-site locates 8/15/94 5:00pm 8/16/94 12:00pm <br /> ......................................................... -------_- <br /> 16 Drill three test borings to approx 8/15/94 5:00pm 8/16/94 5:00pm <br /> ............................. ..................................... ...................................... ................... <br /> 17 , Screen soil samples from TB's 8/15/94 5:00pm -8/16/94 5:00pm <br /> ED <br /> .......... <br /> 18 install one Monitoring Well (MW) 8/15/94 5:00pm 8/16/94 5:00pm <br /> 19 Develop MW's 8/16/94 5:00pm 8/17/94 12:00pm <br /> ............................................................... ................ <br /> 20 Perform petroleum Vapor receptor s 8/17/94 12:00pm 8/17/94 5:00pm <br /> 21 submit samples 8/17/94 5:00pm 8/31/94 5:00pm <br /> ..................................................... ............. ---------- <br /> 22 Draft remedial Investigation repor 8/31/94 5:00pm 9/7/94 5:00pm <br /> 23 Review and complete final report 9/7/94 5:00pm 9/9/94 5:00pm <br /> ......... ............................- <br /> 24 <br /> .................. ........... ........ .... ......... <br /> 25 CORRECTIVE ACTION 9/9/94 5:00pm 9/15/94 5:00pm <br /> Project: Critical Progress Summary <br /> Date: 7/19/94 Noncritical Milestone Rolled Up <br /> Page 1 <br />
The URL can be used to link to this page
Your browser does not support the video tag.