52 <br /> REVISED TIMELINE TO PREPARE AN EAW FOR THE APACHE PLAZA <br /> REDEVELOPMENT PROJECT <br /> TA SK PROPOSED TIMELINE <br /> Data Collection/EAW.Development May 27—July 15, 2003 <br /> City Staff/Council Review of EAW July 15 - 22, 2002 <br /> City Council Authorizes Submittal of EAW July 22, 2003 <br /> to Review Agencies <br /> Submit EAW to EQB Monitor July 28, 2003 <br /> Publication in EQB Monitor August 4, 2003 <br /> EAW Comment Period August 4—September 3, 2003 <br /> Respond to Comments September 3 —5, 2003* <br /> City Staff/ Council Reviews Responses to September 5 - 9, 2003* <br /> Comments <br /> City Council Determines Need for EIS September 9, 2003* <br /> Decision Notice Published in EQB Monitor September 15 or 29, 2003 <br /> *This timeline can be accomplished provided no significant comments are received. If <br /> significant comments are received, it is anticipated the City Council could consider the need <br /> for an EIS at the September 23, 2003 meeting. <br />