St. Anthony Village 41 <br /> Stonehouse Redevelopment <br /> Preliminary Time Line <br /> May 27, 2003 <br /> June 2003: Braun Intertec completes asbestos survey, inclusive of roof samples <br /> June 2,2003: Pre-Redevelopment Agreement sent to Amcon for execution <br /> June 9,2003: Amcon submits update proforma to Ehlers <br /> June 9,2003: Determination made if TIF District is feasible <br /> June 10, 2003: Submit application to Planning Commission for preliminary site plan review (15 <br /> copies— 11 X 17 of site layout and elevations to date) <br /> June 10,2003: Project Team meeting at 10:00—Ehlers Office <br /> June 16,2003: Determination of construction costs related to the new Liquor Store <br /> June 17,2003: Planning Commission Preliminary Site Plan Review—7:00 p.m. <br /> June 17,2003: Submit final plans (civil, building, grading, landscaping, etc) to City for Planning <br /> Commission and City Council review in July <br /> June 19,2003: Ehlers to submit staff recommendation to City Council on preferred redevelopment <br /> option and financial overview <br /> June 24,2003: Project Team meeting at 10:00 a.m.—Ehlers Office <br /> June 24,2003: Review and approval of selected option for redevelopmentby City Council <br /> +i`(ii`e <br /> June 30,2003: Final determination of property to be salvaged frornA& elopment <br /> June-July 2003: Finalize negotiations/terms of Redevelopment�\gr�ement <br /> -. {. <br /> June 24,2003: City Council Preliminary Site Plan' eview <br /> Jul 8 2003: Project Team meeting at 10:00 a.m� Ehlers Office-';�, <br /> Y �` <br /> July- Oct 2003: Submit application for;rlhuor licenseYor nbw restaurant and approval by City Concil <br /> July 2003: Send outbids for asbes�as�abatemenlo commence <br /> 'late August, early September <br /> �+Fv rY:� <br /> July 11, 2003: Dorsey fina zes draft offtvelo meat <br /> Agreement 4 <br /> P <br /> .. <br /> Jul 15 2003: Planning co_inmissior�Fina Site Plan Review, CUP and variance approval <br /> July 17, 2003: _ Ehrs su mits staff ecommpdatto� for approval of Development Agreement <br /> July 22, 2003: d; Pr�'UV-Team meeting at 10 0,a:m —Ehlers Office <br /> tip" iux «- <br /> r. July 22, 2003: r Ci1Coucl FinalSite Plan Review, CUP and variance approval <br /> July 22, 2003: "=' _ Apioval oe eve Agreement by City Council—7:00 p.m. <br /> July 23,2003: Amcon signage can be placed upon the site previewing the new development <br /> September 8,2003;;, = Property closing transaction(both SAV I and Fire Station have relocated) <br /> p.`. <br /> September 9,2003;; Begin asbestos abatement <br /> September 15,2003 Begin demolition/construction <br /> March 2004: Project completed <br />