Laserfiche WebLink
i <br /> • ( ii ) Construction Costs. St. Anthony shall <br /> pay fifty-eight percent ( 58% ) and <br /> Roseville shall pay forty-two percent <br /> (42%) of all amounts paid for the Storm I <br /> Sewer pursuant to the Contract. <br /> F <br /> (b) Street Construction. All engineering , <br /> legal , administrative and construction costs <br /> in connection with the Street Reconstruction <br /> shall be paid by St. Anthony. <br /> (c) Watermain. All engineering , legal, <br /> administrative and construction costs in <br /> connection with the Watermain shall be paid <br /> by Roseville. <br /> 9 . Payment of Project Costs . <br /> ( a) Storm Sewer . At the time the Contract is <br /> awarded, Roseville shall pay St. Anthony <br /> fifty percent (50% ) of the amount the <br /> Engineer estimates as Roseville' s share of <br /> the Project Costs for the Storm Sewer . <br /> After completion of the Storm Sewer and <br /> before final payment to the Contractor is <br /> • due, Roseville shall pay the balance of its <br /> share of the Project Costs for the Storm <br /> Sewer to St. Anthony, based upon the actual <br /> Project Costs for the Storm Sewer . St. <br /> Anthony shall pay its share of the Project <br /> Costs for the Storm Sewer as and when due. <br /> (b) Street Reconstruction. St. Anthony shall <br /> pay the Project Costs for the Street <br /> Reconstruction as and when due. <br /> .( c) Watermain. At the time the Contract is <br /> awarded, Roseville shall pay St. Anthony <br /> fifty percent ( 50% ) of the amount the <br /> Engineer estimates as Roseville' s share of <br /> the Project Costs for the Watermain. After <br /> completion of the Watermain and before final <br /> payment to the Contractor is due, Roseville <br /> Y shall pay the balance of its share of the <br /> Project Costs for the Watermain to St. <br /> Anthony, based upon the actual Project Costs <br /> for. the Watermain. <br /> -6- <br />