Laserfiche WebLink
Option 5 Detailed Costs Continued <br />#ITEM UNIT NO.UNIT COST COST <br />1 GENERAL CONDITIONS <br />1.1 General Conditions, building permits, bonds, insurance, mobilization, contractor 1 1 651,279$ 651,279$ <br />project management, construction superintendent, and contractor profit <br />General Conditions Total Estimated Construction Costs 651,279$ <br />2 GENERAL SITE WORK <br />2.1 Site preparation and tree removal LS 1 9,000$ 9,000$ <br />2.2 Silt fence LF 150 5$ 750$ <br />2.3 Finish grading and turf restoration LS 1 25,000$ 25,000$ <br />2.4 Site utilities LS 1 50,000$ 50,000$ <br />2.5 Pavement LS 1 10,000$ 10,000$ <br />General Site Work Total Estimated Construction Costs 94,750$ <br />3 BUILDING AND PROCESS EQUIPMENT <br />3.1 Excavating and backfilling with select granular material CY 1035 20$ 20,700$ <br />3.2 Structural Pilings LF 1080 50$ 54,000$ <br />3.3 Cast-in-Place Concrete (footings and floor slabs)CY 96 600$ 57,600$ <br />3.4 Precast Concrete LS 1 56350.00 56,350$ <br />3.5 Unit Masonry Assemblies LS 1 209300.00 209,300$ <br />3.6 Misc. Metal Work LS 1 46000.00 46,000$ <br />3.7 Rough Carpentry LS 1 6000.00 6,000$ <br />3.8 Building Insulation LS 1 36800.00 36,800$ <br />3.9 Fully Adhered Membrane Roof System LS 1 66700.00 66,700$ <br />3.10 Caulking and Sealants LS 1 29900.00 29,900$ <br />3.11 Door Frames and Hardware LS 1 12000.00 12,000$ <br />3.12 Painting LS 1 24000.00 24,000$ <br />3.13 Process Piping, Fittings, and Valves LS 1 250000.00 250,000$ <br />3.14 Water Quality Analyzers LS 1 15000.00 15,000$ <br />3.15 Trojan Treatment Equipment and Chemical Feed Systems LS 1 2300000.00 2,300,000$ <br />3.16 Chemical Feed System, Piping and Valves LS 1 150000.00 150,000$ <br />3.17 Flow Meters EA 3 10000.00 30,000$ <br />3.18 Overhead Hoist and Beam LS 1 45000.00 45,000$ <br />3.19 Plumbing and HVAC LS 1 104000.00 104,000$ <br />3.20 Electrical General Provisions LS 1 170000.00 170,000$ <br />3.21 Instrumentation and Controls LS 1 250000.00 250,000$ <br />3.22 UV Replacement Lamps EA 296 1,060$ 313,760$ <br />Building and Process Equipment Construction Costs 4,247,110$ <br />OPTION 5: IMPLEMENT A WATER TREATMENT SYSTEM <br />DETAILED ESTIMATED CAPITAL COST