• EXHIBIT D <br /> SCHEDULE <br /> The Project shall be started within one month of the date a signed contract is received by <br /> BRW. It is anticipated that the work can be completed within 12 months of the date a signed <br /> contract is received. <br /> The following is the approximate schedule of major Project milestones: <br /> Month Milestone <br /> 1 Kick-off meeting with City Council and Planning Commission (Workshop #1) <br /> 3 Submit the draft analysis of conditions and issues (Task 1.3) <br /> 3 Submit draft goals and objectives <br /> 4 Workshop #2 <br /> 5 Submit draft land use plan <br /> 6 Submit draft transportation plan <br /> 6 Submit draft parks and housing plans <br /> 7 Workshop #3 <br /> 8 Workshop #4 <br /> 8 Submit draft implementation program <br /> 9 Workshop #5 <br /> 10 City Council Review <br /> :c <br /> 10 Submit draft plan to Metropolitan Council <br /> 11 Amend Plan <br /> 12 Hold public hearing <br /> 12 Prepare final document <br /> STANCONT.WPD Exhibit C - 2 Rev.,SePlember 30, 1996 <br />