<br /> <br />Project Costs / Recommendation <br /> <br />Gridor Construction, <br />Inc. <br />Rice Lake Construction <br />Group Municipal Builders, Inc. <br />BASE BID $6,267,000.00 $6,273,700.00 $6,385,900.00 <br />BID OPTION NO. 1A (Green Roof) $720,000.00 $717,000.00 $687,700.00 <br />BID OPTION NO. 1B (Painted Roof) $265,000.00 $312,000.00 $253,300.00 <br />BID OPTION NO. 2 (Valve Vault) $7,000.00 $12,000.00 $5,600.00 <br />BID OPTION NO. 3 (Water Tower) $32,000.00 $15,000.00 $15,900.00 <br />BID OPTION NO. 4 (Fire Hydrant) $15,000.00 $15,000.00 $13,500.00 <br />BID OPTION NO. 5 (Canopies) $51,000.00 $23,000.00 $69,400.00 <br />BID OPTION NO. 6 (Seal Well No. 2) $43,700.00 $40,000.00 $43,800.00 <br /> <br />Base Bid + Bid Option No. 1B, 2, 3 & 6 $6,614,700.00 $6,652,700.00 $6,704,500.00 <br />Project Schedule <br />Receive Bids/Award Contract August 23, 2016 <br />Begin Construction September 2016 <br />Start-Up July / August 2017 <br />72