Mirror Lake Temporary Drawdown <br />Public Hearing <br /> <br />September 12, 2017 <br /> <br />Todd Hubmer – City Engineer <br /> <br />Status of Work <br />Completed Work <br />•All tree removal <br />•98 of 125 trees planted <br />•Lake slope correction <br />•Approximately 75% excavation <br />•Installation of erosion prevention <br />storm sewer <br />•Approximately 75% of permanent <br />vegetation establishment <br /> <br />Work to Be Completed <br />•Approximately 25% excavation <br />•Plant 27 remining trees <br />•Install the new outlet control <br />structure. <br />•Create the flood control berm <br />•Final restoration of the new <br />disturbed area <br />41