2019 STREET AND UTILITY IMPROVEMENT PROJECT <br />FEASIBILITY REPORT <br />CITY OF ST. ANTHONY VILLAGE <br />WSB PROJECT NO. R-011648-000 PAGE 11 <br />5. PROJECT SCHEDULE <br />The proposed schedule for this improvement is as follows: <br />Task Completion Date <br />1. Order Feasibility Report.......................................................................................May 22, 2018 <br />2. Accept Feasibility Report and order plans and specifications...................September 11, 2018 <br />3. Hold first public information meeting................................................................November 2018 <br />4. Approve plans/specifications, and order Ad for Bid .........................................November 2018 <br />5. Receive bids ........................................................................................................January 2019 <br />6. Approve resolutions on improvement ..................................................................January 2019 <br />7. Hold second public information meeting ............................................................February 2019 <br />8. Public hearing for project, assessments, award bid, call bond sale...................February 2019 <br />9. Award sale of bonds ...............................................................................................March 2019 <br />10. Begin construction.............................................................................................May/June 2019 <br />11. Certify assessments to a county auditor................................................................August 2019 <br />12. Substantial completion of construction............................................................September 2019 <br />13. Final completion of construction ...............................................................................June 2020 <br />The proposed schedule is estimated and contingent on the schedule to be provided by <br />Hennepin County and Ramsey County <br />73