Laserfiche WebLink
Project Schedule <br />•Open Bids / Compute Assessments January 22, 2020 <br />(7th of 9 Meetings) <br />•3rd Public Informational Meeting March 11, 2020 <br />(8th of 9 Meetings) <br />•Public Hearing / Award Contract April 14, 2020 <br />(9th of 9 Meetings) <br />•Award Sale of Bonds April 14, 2020 <br />•Begin Construction Late April / Early May 2020 <br />•Substantial Completion September 2020 <br />•Final Paving June 2021 <br />Notifications / Additional Information <br />Sign up to receive weekly email updates and <br />notifications by visiting the project webpage <br />located under the tab <br />on the City’s website at <br />http://www.savmn.com <br />60