Laserfiche WebLink
BUILDINGS IMPROVEMENT PROGRAM <br />BLDG <br />YEAR <br />BUILT OR <br />REPLACE <br />D DESCRIPTION LIFE <br />CONDITION GOOD FAIR <br />POOR QTY <br /> COST EST. <br />INTERNAL <br />SEBESTA 2021 <br />EST <br />ACTUAL <br />2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 <br />City Hall 1996 Building Components <br />PARTIAL 2018 Metal Door Frame & Replacement PD and EE Entrances 2018 Multi.Internal -$ -$ -$ -$ -$ -$ -$ -$ 28,000$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ <br />2022 Front Entr. Doors paint / security controls Main Entry set & EE interior Multi.Internal - - 26,500 <br />Council Chamber Doors change-out NA 1 Internal - - - - - - - - - - - - - - - - - - - <br />2016 Security upgrades - Cameras 2016 7 Internal - - - - - - - - 24,313 - - - - - - - - - 30,391 <br />2016 Security upgrades -Control Server 2016 1 Internal - - - - - - - - 17,500 - - - - - - - - - 21,875 <br />2017 Security upgrades - Entrance controls 2017 Multi.Internal - - - - - - - - 24,410 - - - - - - - - - 30,513 <br />2016 Replacement of Fire Alarm Panel 2016 1 Internal - - - - - - - - - - 25,000 - - - - - - - - <br />2015 Parking Lot LED Lighting 2015 Multi.Internal - - - - - - - - - - - - - - - 15,000 - - - <br />2015 Building LED Lighting 2015 Multi.Internal - - - - - - - - - - - - - - - 25,000 - - - <br />2015 Boilers/Fans etc Replaced in 2015-130K 2 Sebesta - - 7,500 - - - 7,500 - - - 7,500 - 160,850 - 7,500 - - - 7,500 <br />2021 RTU-3 (Comm. Services -Adm/Classrooms )Poor -Replace Spring 22 1 Sebesta 64,000 - 98,750 - - - - - - - - - - - - - - - - <br />2020 RTU-4 & DUCKWORK (City) Replaced in 2020 1 Sebesta - - - - - - - - - - - - - - - - - - - <br />RTU-4 & DUCKWORK (City) Replaced in 2020 - - - - - - - - - - - - - - - - - - - <br />RTU-1 (Gym)FAIR -Replace 2023+1 Sebesta - - - 75,000 - - - - - - - - - - - - - - - <br />RTU-2 (Multi-purpose)Replace in Fall 2021 1 Sebesta - 76,200 - - - - - - - - - - - - - - - - <br />2021 RTU-5 (Police)Replaced in 2021 1 Sebesta - 33,200 - - - - - - - - - - - - - - - - - <br />2021 HAVC Controls RTU-3 -(Comm services)update with RTU Units 1 TBD - - 26,300 - - - - - - - - - - - - - - - - <br />2021 HVAC Controls RTU-4 (City)update with RTU Units 1 TBD - 24,800 - - - - - - - - - - - - - - - - - <br />HVAC Controls RTU-1 (Gym)update with RTU Units 1 not required - - - - - - - - - - - - - - - - - - - <br />HVAC Controls RTU-2 (Multi-purpose)update with RTU Units 1 TBD - 12,930 - - - - - - - - - - - - - - - - - <br />2021 HVAC Controls RTU-5 (Police)update with RTU Units 1 TBD - 17,360 - - - - - - - - - - - - - - - - - <br />Domestic Water Heaters Fair 2 Sebesta - - - - - 16,000 - - - - - - - - - - 15,000 - - <br />Relamp & Reballast (LED-PD/City Hall) Done 2015/2021 Multi.Sebesta - 10,652 - - - - - - - - - - - - - 25,000 - - - <br />Roof Poor - Fair 1 Sebesta - - - - - 180,000 - - - - - - - - - - - - - <br />Acoustic panels/overflow AV 2017 1 Internal - - - - - - - - - - - - - 15,000 - - - - - <br />Community Service VCF Tiles 2017 1 Sebesta - - - - - - - - - - - - - 15,000 - - - - - <br />Overhead garage doors 25 years 2 Internal - - - - 15,000 - - - - - - - - - - - - 30,000 - <br />Outdoor sign Fair 1 Internal - - - - 56,000 - - - - - - - - - - - - - - <br />Tuck pointing -brick 35 years 1 Internal - - - - - - - - - - - 140,000 - - - - - - - <br />Parking Lot mill and overlay 30 years 1 Internal - - - - - - 175,000 - - - - - - - - - - - - <br />"Sebesta Type" evaluation of City Buildings - - 15,000 - - - - - - - - - - - - - - - - <br />TOTAL 64,000$ 175,142$ 174,050$ 75,000$ 71,000$ 196,000$ 182,500$ -$ 94,223$ -$ 32,500$ 140,000$ 160,850$ 30,000$ 7,500$ 65,000$ 15,000$ 30,000$ 90,278$ <br />Fire Station 2005 Building Components <br />Metal Door Frame & Replacement Fair Internal - - - 12,500 - - - - - 15,000 - - - - - - - 20,000 - <br />Security upgrades -Cameras 2016 4 Internal - - - - - - - - 8,360 - - - - - - - - - - <br />Security upgrades - Entrance controls 2017 Multi.Internal - - - - - - - - 7,005 - - - - - - - - - - <br />Rooftop Units Fair - Good Multi.Sebesta - - - - 31,000 - - - - - - - - - - - - - - <br />Makeup Air Unit Fair 2 Sebesta - - - 17,500 - - - - - - - - 20,000 - - - - - - <br />Domestic Water Heaters 2016 1 Sebesta - - - - - - 12,880 - - - - - - - - - 15,000 - - <br />Relamp & Reballast Done w/2015 LED project Multi.Sebesta - - - - - - - - - - - - - - - 35,000 - - - <br />Roof Fair 1 Sebesta - - - - - 47,672 - - - - - - - - - - - - - <br />Exterior Paint 2020 1 Internal - - - - - - - - - - - 4,500 - - - - - - - <br />Tuck pointing -brick 35 years 1 Internal - - - - - - - - - - - - - - - 67,500 - - - <br />STATION APPARATUS FLOOR 25 years 1 Internal - - - - - - - - - - 30,000 - - - - - - - - <br />Parking Lot mill and overlay 30 years 1 Internal - - - - - - 35,000 - - - - - - - - - - - - <br />Overhead garage doors 25 years 3 Internal - - - - - - - - - - 60,000 - - - - - - - - <br />TOTAL -$ -$ -$ 30,000$ 31,000$ 47,672$ 47,880$ -$ 15,365$ 15,000$ 90,000$ 4,500$ 20,000$ -$ -$ 102,500$ 15,000$ 20,000$ -$ <br />Public Works 2004 Building Components <br />Metal Door Frame & Replacement Fair Internal - - - 7,500 - - - - - 9,000 - - - - - - - - - <br />Security upgrades -Cameras 2016 3 Internal - - - - - - - - 6,990 - - - - - - - - 8,500 - <br />Security upgrades - Entrance controls 2017 Multi.Internal - - - - - - - - 17,515 - - - - - - - - 22,000 - <br />Rooftop Unit 2017 1 Sebesta - - - - - - 35,000 - - - - - - - - - - - - <br />Makeup Air Unit Good 3 Sebesta - - - - - 19,250 - - - - - - - - - - - - - <br />Air Handling Unit Good 1 Sebesta - - - - - 8,050 - - - - - - - - - - - - - <br />Exhaust Fans Good 6 Sebesta - - - - - 13,340 - - - - - - - - - - - - - <br />Domestic Water Heaters Good 2 Sebesta - - - - 25,861 - - - - - - - - - - - - - - <br />Relamp & Reballast (LED) Done w/2015 LED project Multi.Sebesta - - - - - - - - - - - - - - - - - - - <br />Roof Fair 1 Sebesta - - - - - - - 210,000 - - - - - - - - - - - <br />Overhead garage doors/Shop fixtures 25 years 7 Internal - - - - - - - - - 105,000 - - - - - - - - - <br />Exterior Paint 2020 Internal - - - - - - - - - - - - - - - - - - - <br />Tuck pointing -brick 30 years Internal - - - - - - - - - - - - - - - - - 75,000 - <br />Parking Lot mill and overlay 30 years Internal - - - - - - - - - - - - - - 140,000 - - - - <br />Rehab salt storage 25 years Internal - - - - - - - - - 40,000 - - - - - - - - - <br />TOTAL -$ -$ -$ 7,500$ 25,861$ 40,640$ 35,000$ 210,000$ 24,505$ 154,000$ -$ -$ -$ -$ 140,000$ -$ -$ 105,500$ -$ <br />2