11/14/2022 <br />3 <br />Total Project Costs and Funding <br />Construction Costs <br />Contingency Costs <br />Engineering Costs <br />Total Project Cost = <br />$198,300 <br />Project Cost <br />$146,300 <br />$14,000 <br />$38,000 <br />$198,300 <br />St. Anthony V illage Stormwater Fund <br />Funding Source <br />Harding Pond <br />City of St. Anthony Village, Minnesota <br />Project Schedule <br />•Council Authorizes Plans, Specification and Ad for Bid June 14, 2022 <br />•Open Bids November 9, 2022 <br />•Award Construction Contract November 22, 2022 <br />•Pond Draw Down Late November 2022 <br />•Begin Excavation December 2022 (Weather Permitting) <br />•Final Turf Establishment Spring 2023