4.6 Detour Routes <br />The project will require significant excavation and disposal of unacceptable material from <br />the existing street area and a supply of significant volumes of select granular base, aggregate <br />base, and bituminous pavement materials. This effort will require closing the roads under <br />construction and increasing loaded truck traffic on the streets adjacent to the construction <br />area. Adequately signed detours will be identified to direct traffic around the construction <br />zones and notify users of the increased truck and construction activity. In order to <br />accommodate the property owners along the excavated roads, temporary parking on the <br />adjacent streets may be necessary during the periods when vehicle access is not possible. <br />2013 STREET AND UTILITY IMPROVEMENT PROJECT <br />FEASIBILITY REPORT <br />CITY OF ST. ANTHONY VILLAGE <br />WSB PROJECT NO. 1626-66 <br />PAGE <br />35 <br />