Document: RES 81-027 RESOLUTION AUTHORIZING THE MAYOR AND
CIN MANAGER TO EXECUTE THE JOINT POWERS AGREEMENT
BETWEEN ST. ANTHONY AND ROSEVILLE FOR STORM SEWER; STREET
IMPROVEMENT AND WATER MAIN CONSTRUCTION
RESOLUTION 81-027
A RESOLUTION AUTHORIZING THE MAYOR AND
CITY MANAGER TO EXECUTE THE JOINT POWERS
AGREEMENT BETWEEN ST. ANTHONY AND ROSEVILLE
FOR STORM SEWER, STREET IMPROVEMENT AND
WATER MAIN CONSTRUCTION
BE IT RESOLVED that the Mayor and City Manager are
authorized to execute the Joint Powers Agreement
between St. Anthony and Roseville for storm sewer,
street improvement and water main construction on .,
behalf of the City of St. Anthony.
Adopted thisage day of Apr-; l 1981.
T
i
M or
ATTEST:
City Clerk
Reviewed for administration:
City Mana
JOINT POWERS AGREEMENT
BETWEEN ST. ANTHONY AND 'ROSEVILLE
FOR STORM SEWER, STREET IMPROVEMENT
AND WATER MAIN CONSTRUCTION
THIS AGREEMENT is made as of "
���L���
1981 , by and between the CITY OF ST. ANTHONY," a municipal
corporation under the laws of the State of Minnesota
( hereinafter called "St. Anthony" ) and the CITY OF
ROSEVILLE, a municipal corporation under the laws of the
State of Minnesota ( hereinafter called "Roseville" ) .
WITNESSETH THAT:
WHEREAS , St . Anthony and Roseville ( hereinafter
sometimes collectively called the "Cities" ) eac,h 'have
certain powers common to both Cities , including the power
to construct storm sewers, street reconstruction and water
mains;
WHEREAS , certain economies of scale can be
achieved if the Cities jointly and cooperatively exercise
the powers described above;
WHEREAS , Minnesota Statutes §471 . 59 provides that
two or more cities, by agreement entered into through the
action of their governing bodies , may jointly or
cooperatively exercise any power common to the cities ,
including .those powers which are the same except for the
territorial limits within which they may be exercised;
WHEREAS , Minnesota Statutes §471 . 59 further
provides that an agreement for such joint exercise of
powers may provide for the exercise of such powers by one
of the cities on behalf of the other ;
WHEREAS , the City Councils of both Cities have
determined that it will be in the best interest of their
respective Cities to jointly and cooperatively exercise
such powers in the manner provided for herein , and that
the same shall be for the mutual benefit of the Cities;
WHEREAS , the Cities desire to commence a single ,
joint construction project ( hereinafter called the
"Project" ) consisting of the following three ( 3) parts:
( a) The installation of a storm sewer system to
•. drain certain areas of both St. Anthony and
Roseville;
(b) The reconstruction of a portion of Anthony
Lane North located entirely within St.
Anthony; and
( c) The construction of a municipal trunk
watermain loop system to be located entirely
within Roseville;
WHEREAS , the Cities wish to set forth their
agreements and understandings relating to the Project and
the sharing by the C-ities of the cost thereof.
NOW THEREFORE, in consideration of the above
premises and of the mutual. convenants and agreements
contained herein , the Cities hereby agree as follows:
•
-2-
• 1 . Project Engineer . The Cities mutually agree
upon the firm of Short, Elliott, Hendrickson, Inc.
( hereinafter called the "Engineer " ) to, do the engineering
work in connection with the Project.
2. Administration of this Agreement and the
Project. This Agreement and the Project, and related
matters including the advertisement for bids and the award
of a construction contract for the Project, shall be
administered by St. Anthony, with advice and consultation,
and supervision of the Project, by the Engineer .
3 . Preparation of Plans; Description of
Project. As soon as is reasonably possible,-- the Engineer
shall cause construction plans and specifications to be
• prepared for the Project ( hereinafter called the
"Plans" ) . The Plans shall be divided into the following
three ( 3 ) sections:
( a) Section I . A storm sewer system
( hereinafter called the "Storm Sewer" ) to
drain certain areas within St. Anthony and
Roseville. These areas shall be as
designated in the Joint Power Agreement
Storm Sewer Feasibility Study prepared by
Short , Elliott , Hendrickson, Inc. and dated
November , 1950 . The Storm Sewer shall be
constructed in the right-of-way of Anthony
Lane North in St. Anthony and in an easement
to be obtained by Roseville over certain
property in Roseville adjoining the St.
Anthony property.
( b) Section II . Street reconstruction
( hereinafter called the "Street
Reconstruction" ) for Anthony Lane North from
Ramsey County Road "C" to a terminus
-3-
• approximately 900 feet northeasterly of
Ramsey County Road "C" . The Street
Reconstruction will be entirely within the
boundaries of St. Anthony and within the
existing right-of-way of Anthony Lane North.
( c) Section III . A municipal trunk watermain
loop system ( hereinafter called the
"Watermain" ) . The Watermain shall run
between Ramsey County Road "C" and County
Road "C-2" in a northerly and easterly
direction. The Watermain will be entirely
within- the boundaries, of Roseville and
within existing easements in favor of
Roseville or easements to be acquired by
---__ _Roseville at its sole expense prior to the
award___qf any contract for the Project.
4 . Submission of Plans—to the City Councils. As
soon as the Plans have been obtained, St. Anthony shall
submit the Plans to the City Councils of both Cities for
review and approval. If either City fails to approve the
• Plans within thirty ( 30) days after they are submitted to
that " City' s Council, either City shall have the right to
terminate this Agreement by written notice to the other .
If the Plans are approved by the City Councils of both
Cities, St. Anthony shall proceed with advertisements for
bids.
5 . The Construction Contract. The construction
contract for the Project ( hereinafter called the
"Contract" ) shall include provisions for the following :
( a) A comprehensive liability insurance policy
to be obtained by the Contractor and naming
both of the Cities as insureds.
( b) Indemnification of both Cities by the
Contractor .
•
-4-
(c) Payment and performance bonds in the full
amount of the Contract to be obtained by the
Contractor and naming both Cities as
obligees .
6 . Bidding and Award of the Contract. After the
Plans have been approved by the City Councils, St. Anthony
shall advertise for -construction bids , and each. City shall
determine whether to accept a bid and award the Contract.
If all bids . are rejected , St. Anthony may re-bid the
Project or may terminate this Agreement by written notice
to Roseville. If the lowest responsible bidder , based on
the total bid for the entire Project, is acceptable to
both Cities , both City Councils shall adopt appropriate
resolutions awarding the Contract to the contractor who
• made such bid ( herein called the "Contractor" ) . Any
change orders to the Contract shall require the approval
of each City.
7 . Execution .of the Contract. St. Anthony and
the Contractor shall execute the Contract.
8 . Sharing of Project Costs . The costs of the
Project (hereinafter called the "Project Costs" ) shall be
shared as follows:
( a) Storm Sewer .
( i) Engineering , Legal and Administrative
Costs. St. Anthony shall pay
fifty-eight percent ( 58% ) and Roseville
shall pay forty-two percent (42% ) of
all out-of-pocket engineering, legal
and administrative costs incurred by
St.' Anthony in connection with the
• Storm Sewer .
-5-
i
• ( ii ) Construction Costs. St. Anthony shall
pay fifty-eight percent ( 58% ) and
Roseville shall pay forty-two percent
(42%) of all amounts paid for the Storm I
Sewer pursuant to the Contract.
F
(b) Street Construction. All engineering ,
legal , administrative and construction costs
in connection with the Street Reconstruction
shall be paid by St. Anthony.
(c) Watermain. All engineering , legal,
administrative and construction costs in
connection with the Watermain shall be paid
by Roseville.
9 . Payment of Project Costs .
( a) Storm Sewer . At the time the Contract is
awarded, Roseville shall pay St. Anthony
fifty percent (50% ) of the amount the
Engineer estimates as Roseville' s share of
the Project Costs for the Storm Sewer .
After completion of the Storm Sewer and
before final payment to the Contractor is
• due, Roseville shall pay the balance of its
share of the Project Costs for the Storm
Sewer to St. Anthony, based upon the actual
Project Costs for the Storm Sewer . St.
Anthony shall pay its share of the Project
Costs for the Storm Sewer as and when due.
(b) Street Reconstruction. St. Anthony shall
pay the Project Costs for the Street
Reconstruction as and when due.
.( c) Watermain. At the time the Contract is
awarded, Roseville shall pay St. Anthony
fifty percent ( 50% ) of the amount the
Engineer estimates as Roseville' s share of
the Project Costs for the Watermain. After
completion of the Watermain and before final
payment to the Contractor is due, Roseville
Y shall pay the balance of its share of the
Project Costs for the Watermain to St.
Anthony, based upon the actual Project Costs
for. the Watermain.
-6-
4 '•
• I
10 . Cooperation. St. Anthony and Roseville
agree to cooperate fully with each other and with the
Engineer so that the Plans may be prepared and the Project
completed as soon as possible.
11 . Indemnification. The Contract shall provide
for indemnification of both Cities by the Contractor .
Neither City shall be responsible for , or in any manner
liable for , any claim, demand, action or cause of action
of any kind arising out of St. Anthony' s performance or
failure to perform under this Agreement, whether based on
negligence or otherwise. ,
12. Liability Insurance . Each City agrees to i
maintain comprehensive general liability insurance in i
• reasonable amounts protecting itself from liability with
respect to accidents occurring within its territorial
limits or arising out of the performance of this
Agreement, and for injuries or deaths arising out of any
accidents- related to the Project or this Agreement.
9
13 . Employees. No employee or official of
e.ither. of the Cities shall at any time or in any manner be
6.
deemed to bean employee or official of the other City by
reason of the performance of work or the providing of
services within the territorial limits of the other City,
or on behalf of the other City, pursuant to this Agreement.
I
SII
-7-
i
i
I
y
i
• . 14 . Disbursement of Funds. Both Cities hereby
agree that public funds may be disbursed to St. Anthony in
the manner provided in this Agreement to carry out the
purposes .hereof. Any contract let or purchase made in 1
connection with this Agreement shall conform to applicable I
requirements of state law. St. Anthony shall strictly
account for all funds disbursed pursuant to this Agreement
and shall report to Roseville concerning all receipts and
disbursements in connection with this Agreement.
15 . Assignment. This Agreement may not be
assigned by either party hereto without the prior written
consent of the other party; provided, howeve-r , that St.
Anthony may contract with other, parties and may employ
• individuals to perform the services to be performed by it
hereunder .
16 . Modification. This Agreement embodies the
entire Agreement between the Cities with respect to the
subject matter hereof, and all prior discussions ,
negotiations and agreements are merged herein. This
Agreement may be amended or modified only by an agreement
in writing authorized by the City Councils of both Cities
and executed on behalf of both Cities.
17 . Term of this Agreement. The term of this
Agreement shall extend through the date of completion of
the Project or termination of the Agreement as herein
-8-
• provided and through full reimbursement of St. Anthony by I
Roseville for its share of the costs provided, for herein.
18 . Notices. The following persons are hereby
designated as the principal contact persons for the
Project, and all notices and communications should be
directed to them:
City of St. Anthony: Larry Hamer
City of Roseville: Charles Honchell
IN WITNESS WHEREOF, the parties hereto have
• caused this Agreement to be executed as of the day and
year first above written..
CITY OF ST. ANTHONY
By24��
Its Mayor
And
is City nager
-9-
i
• CITY OF ROSEVILLE
By
Its Mayor
And
is City anager