HomeMy WebLinkAboutRES 84-020 RESOLUTION AUTHORIZING THE MAYOR AND CITY MANAGER TO SIGN THE CONSTRUCTION COOPERATIVE AGREEMENT WITH HENNEPIN COUNTY REGARDING THE COUNTY ROAD "D" PROJECT Meeting Sheet
IIIIIIVIIIVIIIVIIIVIIIVIIIIIIIIIII
102487
Box: 23
Folder: RES 1984
Document: RES 84-020 RESOLUTION AUTHORIZING THE MAYOR AND
CIN MANAGER TO SIGN THE CONSTRUCTION COOPERATIVE
AGREEMENT WITH HENNEPIN COUNTY REGARDING THE COUNTY
ROAD "D" PROJECT
•
RESOLUTION 84-020
A RESOLUTION AUTHORIZING THE MAYOR AND CITY MANAGER
TO SIGN THE CONSTRUCTION COOPERATIVE AGREEMENT
WITH HENNEPIN COUNTY REGARDING THE
M COUNTY ROAD "D" PROJECT
WHEREAS, Ramsey County is preparing plans and specifications for
Ramsey County Road "D" project, which construction will include
portions located in the Hennepin County portion of the City of
St. Anthony; and
WHEREAS, the City of St. Anthony will share in the Hennepin County
cost share of said project asset forth in the Construction Co
operative Agreement No. PW 11-10-84 .
NOW, THEREFORE, BE IT RESOLVED, that the Mayor and City Manager
are hereby authorized to sign .the Construction Cooperative
• Agreement No. PW 11-10-84 between the City of St-. Anthony and
Hennepin County.
Adopted this p day of AKA Li I 1984 .
May r
ATTEST:
City Clerk
Reviewed for administration: m,
City Manager
� C
DEPARTMENT OF TRANSPORTATION = :p1N�-_.4
320 Washington Av. South
FTHopkins, Minnesota 55343ES
NNES�
HENNEPIN
LFU 935-3381
TTY 935-6433
March 8, 1984
Mr. David M. Childs, Manager
City of St. Anthony
3301 Silver Lake Road
- Minneapolis, Minnesota 55418
AGEEEMENT NO. PW 11-10-84
S.P. 62-619-04 & S.P. 27-693-01
CSAH 93 (37TH AVE. N.E. )
COUNTY PROJECT 7205
Dear Mr. Childs:
Enclosed are two copies of a Construction Cooperative Agreement for the
above referenced project for which arrangements are being made to call for
bids. This project is being constructed by Ramsey County.
• The agreement covers the cost sharing by Hennepin County and the City of St.
Anthony for the portion of the project within Hennepin County.
If the agreement is satisfactory, please have both copies signed by the
.appropriate city officials and return them to this office. Upon completion
of the remaining signatures by county officials, we will send you one fully
executed copy for your. files. Also, please return a certified copy of the
resolution authorizing the mayor and - to sign the agreement. -�
e�
If you have any questions concerning the agreement, please contact me'.
Sin erel
ern Gen ger E.
Chief, sign vision
VG/WGM: lar
Enclosures
HENNEPIN COUNTY
an equal opportunity employer
y<!- u
Agreement No. PW 11-10-84
Hennepin County Project No. 7205
County State Aid Highway No. 93
• City of St. Anthony
County of Hennepin
CONSTRUCTION COOPERATIVE AGREEMENT
AGREEMENT, Made and entered into this 'x_�day of ^Mam 19 Tly—, by �,C_
and between the County of Hennepin, a body politic and corporate under the laws of the
State of Minnesota, hereinafter referred to as "Hennepin County" and the City of St.
Anthony, a body politic and corporate under the laws of the State of Minnesota,
hereinafter referred to as the ."City".
WITNESSETH:
WHEREAS, Ramsey County is preparing plans and specifications for construction of
• Ramsey County Road "D" and Hennepin County State Aid Highway No. 93 between Beldon
Drive and Interstate 35W west ramps. Said plans and specifications labelled and
identified as S.P. 62-619-04 and S.P. 27-693-01 are by this reference made a part
hereof; and
WHEREAS, That portion of. said County State Aid Highway .No. 93, included in said
Ramsey County plans, located between Beldon Drive and the easterly limits of Hennepin
County (Engineers Station 5+10 to Engineers Station 26+29.72) is hereinafter known and
referred to as Hennepin County Project No. 7205. Said Hennepin County Project 7205
lies within the corporate limits of the City; and
-WHEREAS, Hennepin County and Ramsey County are negotiating a construction
cooperative agreement covering County cost participation in a contract to be let by
Ramsey County for construction of said Hennepin County Project 7205; and
•
-1-
• WHEREAS', The estimated Hennepin County cost share for the construction of said
Hennepin County Project No. 7205 is $499,398.65, and
WHEREAS, A portion of the aforementioned Hennepin County cost share is subject
to reimbursement by the City in accordance with Hennepin County's standard division of
cost policy for construction of highways within corporate limits of municipalities,
said reimbursement and the Hennepin County cost share is shown in EXHIBIT A attached
hereto and, made a. part hereof; and_
WHEREAS, It is contemplated that the work be carried out by the parties hereto
under the provisions of M.S. Sec. 162. 1.7, Subd. 1.
NOW THEREFORE, IT IS HEREBY AGREED:
' I
Ramsey County or its agents under the proposed agreement with Hennepin County,
will advertise for bids for the work and construction of the aforesaid Project No.
7205, receive and open bids pursuant to said advertisement and enter into a contract
with the successful bidder at the unit prices specified in the bid of such bidder,
according to law in such case provided for counties. The Contract will be in form and
will include the plans and specifications prepared by Ramsey County or its agents.
LI
Said .agreement also requires that Ramsey County administer the contract and
inspect the construction of the contract work contemplated herewith. However, the City
Engineer of St. Anthony shall cooperate with the Ramsey County Engineer and his staff
• at their request to the extent necessary, but will have no responsibility for the
supervision of the work.
-2-
• III
Hennepin County or its agents shall acquire all rights of way, permits and/or
easements required for the construction of said project No. 7205.
The final cost of all rights of way, permits and/or easements required for the
construction of said project plus all costs incurred by Hennepin County in acquiring
said rights of way, permits and/or easements shall be apportioned 50 percent to
Hennepin County and 50 percent to the City of St.. Anthony—
The right of way costs incurred as described herein shall include all acquisition
costs including, but not limited to, any and all damages occurring to any person or
persons, including private utilities, in relocating or removing or adjusting main
conduits or other structures located in or upon the land taken and within the present
right of way; or damage in procuring such right of way, whether such damage is caused
• by the Counties or the City in the performance of such contract with respect to the
improvement of County State Aid Highway No. 93, as shown on the plans for Hennepin
County Project No. 7205.
Hennepin County will periodically, as parcels are acquired, prepare and submit to
the City itemized accounts showing right of way and acquisition costs incurred by
Hennepin County. The City share of said costs shall become due and payable within
thirty (30) days after submittal.
Takings in excess of that required for the roadway construction will only be
accomplished if the parties hereto mutually agree that said excess takings are
desirable. The cost of any such excess taking will be shared 50% Hennepin County - 50%
City and all costs and receipts from rental or sales after acquisition will also be
shared on the same basis.
•
-3-
• The estimated right of way expenses described herein are indicated in said
EXHIBIT A attached hereto.
IV
The City shall reimburse Hennepin County for its share in the contract
construction costs of said Hennepin County Project No. 7205 and the total final
contract construction costs shall be apportioned as set forth in the Division of Cost
statement in said EXHIBIT A attached hereto. It is further agreed that the amounts
shown in EXHIBIT A are based upon estimated quantities at estimated unit prices and
that the unit prices set forth in the contract with the successful bidder and the final
quantities as measured by the Ramsey County Engineer shall govern in computing the
total final contract construction cost for apportioning the cost of said project
according to the provisions of this paragraph.
•
V
In addition to payment of the City's proportionate share of the contract
construction and right of way costs, the City also agrees to pay to. Hennepin County a
sum equal to thirteen percent (13%) of the amount computed as the City's share of the
said contract construction costs, it being understood that said additional payment by
the City is its proportionate share of all engineering costs incurred in connection
with the work performed within the corporate limits of the City on this project.
VI
Within sixty (60) days after an award by Ramsey County to the successful bidder,
the City shall deposit with the Hennepin County Treasurer, ninety percent (90%) of the
estimated City share in the contract construction and engineering costs for said
-4-
• project No. 7205. Said estimated City share shall be based on actual contract unit
prices for estimated quantities shown in the plans.
The remaining ten percent (10%) is to be paid to Hennepin County upon the
completion of said project and submittal to the City of the Final Estimate for the
project showing the City's final share in the contract construction and engineering
costs.
Upon payment of the Final Estimate to the successful bidder, any amount remaining
as a balance in the deposit account will be returned to the City; likewise any amount
due Hennepin County by the City upon payment of the Final Estimate shall then be paid
by the City as its final payment for the construction and engineering cost of this
project.
• VII
Hennepin County reserves the right not to issue any permits for a period of five
(5) years after completion of the project for any service cuts in the roadway surfacing
of the County Highway included in this project for any installation of underground
utilities which would be considered as new work; service cuts shall be allowed for the
maintenance and repair of any existing underground utilities.
VIII
It is agreed that Hennepin County, at its expense, shall place all necessary no
parking signs and'the City, at its expense, shall provide the enforcement for the
prohibition of on-street parking within its corporate limits on that portion of County
State Aid Highway No. 93 constructed under this project.
-5-
• Any modification of the above parking restriction shall not be made without first
obtaining a resolution from the Hennepin County Board of Commissioners permitting said
modification.
IX
All records kept by the City and Hennepin County with respect to this project
shall be subject to examination by the representatives of each party hereto.
X
It is agreed that the City shall remove and replace all City owned signs that are
within the construction limits of this project, all at City expense.
XI
It is further agreed that each party to this agreement shall not be responsible
or liable to the other or to any other person or persons whomsoever for any claims,
damages, actions, or causes of actions of any kind or character arising out of or by
reason of the performance of any work or part hereof by the other as provided herein;
and each party further agrees to defend at its sole cost and expense any action or
proceeding commenced for the purpose of asserting any claim of whatsoever character
arising in connection with or by virtue of performance of its own work as provided
herein. It is agreed that the City will be included as a named insured under the
liability insurance policy required to be provided by the Contractor performing the
work under said Project No. 7205.
•
-6-
• XII
It is further agreed that any and all employees of the City and all other person
engaged by the City in the performance of any work or services required or provided for
herein to be performed by the City shall not be considered employees of Hennepin
County, and that any and all claims that may or might arise under the Worker's
Compensation Act or the .Unemployment Compensation Act of the State of Minnesota on
behalf of said employees while so engaged and any and all claims made by any third
parties as a consequence of any act or omission on the part of said employees while so
engaged on any of the work or services provided to be rendered herein shall in no way
be the obligation or responsibility of Hennepin County.
Also, any and all employees of Hennepin County and all other person engaged by
Hennepin County in the performance of any work or services required or provided for
herein to be performed by Hennepin County shall not be considered employees of the
•
City, and that- any and all claims that may or might arise under the Worker's
Compensation Act or the Unemployment Compensation Act of the State of Minnesota on
behalf of said employees while so engaged and any and all claims made by any third
parties as a consequence of. any act or omission on the part of said employees while so
engaged on any of the work or services provided to be rendered herein shall in no way
be the obligation or responsibility of the City.
XIII
The provisions of M.S. 181.59 and of any applicable local ordinance relating to
civil rights and discrimination and the affirmative action policy statement of Hennepin
County shall be considered a part of this agreement as though fully set forth herein.
•
-7-
XIV
Should the Counties of Hennepin and Ramsey fail to enter into the construction
cooperative agreement mentioned on page one of this agreement, then in that' .event, this
agreement between Hennepin County and the City shall be null and void.
•
•
-8-
s
• IN TESTIMONY WHEREOF, The parties hereto have caused this agreement to be executed
by their respective duly authorized officers as of the day and year first above
written.
CITY OF ST. ANTHONY
(Seal) By
iayor
Date: • .. z„r•. 9u
And: 11 11�YyVU.X
Ct`y Manager
Date:
COUNTY OF HENNEPIN
ATTEST:
C" By:
erk of the County Board T Ch an of its County Board
064
Date: '5-Az Date:
And:
Upon proper execution, this agreement Associat Co a y Administrator
will be legally valid and binding. and County E gineer
By: L`-✓ �C� ���' Date:
Assistant County Attorn y
Date:
RECOMMENDED FOR APPROVAL
Approv cWi to execution _ Q
By: 4—"
By: Director, Department of Transportation
Assistant County Attorney
Date:
• Date: �� yj
E x r� � ewt- A � • .
PAGE NO.. 1 102/29/84 JnB tin. 205
COST ESTIMATE FPR C.S.A,H. Nn. 93 pRnJ. Nn. ?poli
ITEM ITEM APPROXTMATF UNIT
NUMAER DESCRIPT16N QUANTTTY UNIT PRICE AMOUNT
20121'.50t MOBILIZATION .22 LU""P SUM 800010,00 17620.00'
2101.502 CLEARING t58.0M TRFE 83.00 13114,04
2101 .507 GRUBBING 145.010 TREE 50.(00 725P.0�'
2t04r5at REMOVE CURB AND GUTTER 11RV.►,0m ON FT 1 .50 1770,00 ;
2100.501 REMOVE CuRR 370,00 LIN FT 1 .Sa 555.00'
2104x501 REMOVE PIPE C11L.VERT 50.0A LIN FT 4,501 225,90
2104rSolPENOVE PIPE CULVERT 333,001 LIN FT 6,OP 1998.00
2104.503 REMOVE SIDEWALK 140.AP SG FT .60 84.01n
2104r54S RFMOVE CONCRETE PAVEMENT A49o(Ao SW YD 2.85 2419,65
2104.509 REM. CATCH BASINS nR S1:iRFACE DvAIN S.UM EACH 150.0 ! 758.V1A
2104x521 SALVAGF CHAIN LINK FENCE 2JS,00 LIN FT loop 215,00
2104x521 SALVAGF WOOD RAIL FENCE 60.09 LIN FT 1 ,10 60.Am
2104.5?l SALVAGF w00D PRIVACY FENCE 160,001 LIN FT i.Q9 16001??
2104..523 SALVAGE HYDRANT 1 .09 EACH 400.A0 49V,00
2105SolCOMMON EXCAVATION (P) 26731 .He� CU YD 1.85 4905209
2105x523 COMMON BMRROW (Lv) 437?,UM CU YD 3.25 t42?+9.A"
2105x525 TOPSOIL BORROW (LV) 6?5,MM CU Yn 5.25 3281 .25
2t3P.501 WATER 42,00 !0001? GAL 12.00 SA4.00
2211x5911 AGGREGATE BASE CLASS 3 5(495.00 TON 4.Sm 22927,50
2211,501 AGGREGATE RASE CLASS 4 3921 ,00 TON I1151" 17194.50
2211.x5A1 AGGREGATE RASE CLASS 6 4541 ;00 TON 6.25 28381 .25
230fxSol 7 1/2" NON•RFTNFORCED CONC. PAV'T 553.00 SO YD 6.AA 3318,01 '
2301 .St1 STRUCTURAL CONCRETE 115.00 CU YO 40.NP 46A0.0A
231011529 REINFORCEMENT AAPS 244,@M POUNn .?fA 170.80
0301x604 SAWCUT CONCRETE PAVF,MENT 6011 .00 LIN FT 1.60 96t.6n
2331..504 SIT MATERIAL. FOR MTXTURE 175.00+ TON 170.00+ 24750.00
23310SW8 WEARING COURSE. MIXT. FOR ENTRANCES 88.00 TON 20.49 1760000
2331x510 BINDER CnuRSE MIXT11RF 945.00 TON 9.94 9402.75
2331x514 BASE COURSF MIXTURF 2727,001 TON 9.80 26724.60
033.1x601 IIT. MAT'L FOR TFMP SURFACING 1942.OM SO YO 2.90 5631.80
0331 .6913 SAWC11T BITUMINOUS PAVEMENT SURFACE 837,00 LIN FT 1 .501 1255.50
2357x502 BIT MATERIAL FOR TACK COAT 1624.OM GAL 1.25 2030,00
2361x504 ASPHALT CEMENT 46.00 TON 17H,NP 782000M
2361 .509 WEARING COURSE MIXTURE 654.00 TON 19.0 ' 12426.0 '
0427_x607 TI"!hCR MALL 938.090 SO FT 6.30 5909.40
2503x541 15 RC PIPE SEWER CL TV DES 3906 1562,00 LIN FT 24.50+ 38269.Na
2503.541 18 RC PIPE SEWER DESIGN W6 1256.00 LIN FT 27.OP 33912.00
2503.541 21 RC PIPE SEWER OFSI'GN 3n 0b 127.0+0 LIN FT 30.001 3810,00
OSO4. 602 INSTALL HYDRANT 1 .00 EACH 455.0fA 455.00'
05N4�6P7 6" VALVE BOX A'RD ASSFMNLY 1 ,00 ASSEMPLY 4501.0F 45P.a�"
2506.5013 CONST MANHOLES DESIGN A OR F 10.30 EACH ta00.WP 1PPQ10.W� '
E #T 'A
PAGE N0 , 2 P2/2P/84 JnB N0. 20S
ITEM ITEM APPROXIMATF )NTT
NUMSER nESCRIPTIRN 00ANTITY UNIT PRICE AMOUNT
2506'509 CONCSTRUCT CATCH BASIN DESIGN 8Pw2 8.00 EACH A5N.0A 60100,0m
25060504 CONST CATCH 9ASINS DESIGN LP4.4 1 .00 EACH 12a0.AA 1200.0 +
2506,509 CONST CATCH BASINS DESIGN Lp4.5 6.AM EACH 0100M 78�Ip.0p '
2506.509 CONST CATCH BASINS DESIGN LP4.6 1 .p0 EACH 13510.dP 1350.00
2506;511 RECONSTRUCT MANHOLES 5.00 LIN FT i65.ea 825.A�
2506,516 CASTING ASSEMBLIES 1'.010 EACH 250.00 25o+.Ao+
2506,521 INSTALL CASTINGS 1 :00 FACH 175.0A 175.Ao+
2506'522 ADJUST FRAME AND RING CASTINGS 3.09 EACH 175.00 525.00
2521,591 4" CONC. WALK FOR MEDIANS 1179.00 SO FT 1.SR !76.8.50
2531..5011 CONIC C AND G DESIGN gbt2 444.00 LIN FT 5.45 2419.80
2531 ,501 CONC C AND G DESIGN 8624 3906.0M LIN FT S965 2206A.90
2531,5(42 CONC CURB DESIGN V6 861 .00 LIN FT 5.AA 43M5.00
2531,507 6 CONC DRIVEWAY PAVEMENT 385.0A SO YC 19.00 7315.0p
0557..603 INSTALL WOODRAIL FENCE 60.00 LIQ! FT 1.50 90.00
0557,603 INSTALL WOOD PRIVACY FENCE 160.00 LIN FT 2.25 360.09
0557,603 INSTALL CHAIN -LINK FENCE 215.00 LIN FT 3.75 8016.25
0563,601 TRAFFIC CONTROL .22 LUMP SUM 220m0.90 4840000
0564,602 PAVEMENT MESSAGE LT. ARROW 1 .0P FACH 8a.isp �1P.(0P
N564.603 4" SnL. LINE YEL. POLYMER PREFMn 14A0.9I01 LIN FT 1 ,5ol 222NOO
0564,603 4" SbL. LINE YEL, EPnXY 6760!.00 LIN FT 037 25P11 .2M
N564,603 4" SOL. LINE wHT. FPDXY 65.00 LIN FT .37 24.01F
0564..603 4" SPOKEN LINE WHITE EPnXY 250.01 LIN FT .37 42.50
0564r603 24" SOLID LINE WHITE EPDXY 66.0a LIN FT 4.25 280.50
2565,511 FULL T ACT T CnmTRnL SIG. SYS. A .50 SIG SYS eg0a0.0a 42SP0.00
2575,505 SODDING 7505.00 SG YD 1 .AG1 7595.00
el a elm
2575.531 COMM. FERT. ANALYSIS 12®12.12 .3q TON 3A0.0a 98,65
SUBTOTAL 494398.65
TOTAL ESTIMATED COST 499348.65
• DIVISION OF COST
EXHIBIT A CSAH 93
PAGE 3 OF' 3 FRON_9ELDON DRIVE TO EAST COUNTY LINE -(HIGHCREST ROAD),_ _
HENNEPIN COUNTY PROJECT 7205, S.P. 27-693-01
C TOTAL % COST % COST j
ESTIMATED ESTIMATED ESTIMATED HENNEPIN 'HENNEPIN CITY OF CITY OF
ITEM UNIT QUANTITY UNIT COST COST COUNTY COUNTY ST. ANTHONY ST. ANTHONY °(
CONCRETE CURB 8 GUTTER. DESIGN 8624 LIN. FT. 2655 $ 5.65 $ 15.000.75 50 $ 7,500.38 50 $ 7,500.37 .I
(ON 37TH AVE. ONLY) "�
STORM SEWER (CATCH BASINS AND LEADS) {
DESIGN SP-2-C.B. NOS. 101,102.106.107, EACH 8 850.00 6.800.00 50. 3.400.00 50 3.400.00
120.121.122.133
DESIGN LP4-4 -. C.B. NO. 112 EACH 1 1.200.00 1.200.00 50 600.00 50 600.00
1 DESIGN LP.4-6 - C.B. NOS. 105.113.119. EACH 6 1.300.00 7.800.00 50 3.900.00 50. ` 3,900.00 i
i 124.127.131
! DESIGN LP4-6 - C.B. NO. 117 EACH 1 1.350.00 1.350.00 50 675.00 50 675.00 -
150 REINFORCED CONCRETE PIPE LIN. FT. 591 24.50 14.479.50 50 7.239.75 50 7.239.75 k
STORM SEWER (NON-PARTICIPATING) (1) 8.567.87 - 100 8.561.87
TIMBER WALL SQ. FT. 938 6.30 5.909.40 50 2.954.70 50 2.954.70
FULL TRAFFIC-ACTUATED TRAFFIC CONTROL SYSTEM 0.5 85.000.00 42.500.00 50 21.250.00 50 .-21.250.00
SIGNAL SYSTEM A
Is 6" VALVE BOX ANO.ASSEMBLY ASSEMBLY 1 450.00 450.00 0 100 450.00
V SUBTOTAL $104.057.52 $47.519.83 $56.537.69
i
BALANCE OFCONSTRUCTION _5395.341,13 $ 95.341.13 F
TOTAL ESTIMATED COST FOR'CONTRACT.ITEMS $499.398.65 $442.B6O,96_ $56.537.69 i
PLUS 13% FOR ENGINEERING 8 CONTRACT ADMINISTRATION (SUB-TOTAL) 7.349.90
s LESS 76.74% FEDERAL PARTICIPATION FOR'ALL 0NTRACT ITEMS EXCEPT 36.466.71
STORM SEWER (NON-PARTICIPATING) AND' 6' VALVE BOX AND ASSEMBLY
RIGHT OF WAY 255,000.00 50 127.500.00 S0 127,500.00 !
TOTAL ESTIMATED COST - ST. ANTHONY'S ;. $154.920.88
(1) BASED ON THE RATIO OF CONTRIBUTING'AREAS WITH STATE AID FUNDS AND INPLACE OUTFALL
LINES CREDITED AS SHOWN IN MN/DOT'S HYDRAULIC HEMO DATED SEPTEMBER 27. 1982. a ',
AMOUNT IS EQUAL TO 3.1% OF TOTAL STORM SEWER COST FOR PROJECT ON RAMSEY CR 'D'
FROM SILVER LAKE ROAD TO CLEVELAND AVENUE j
AWH:lar
2/10/84