RESOLUTION 79-025
A RESOLUTION APPROPRIATING FUNDS
FOR WELL NO. 3 REPAIRS
Whereas , the amount of money budgeted for Well No. 3
repairs in the 1979 Budget is insufficient.
Whereas, the City Council deems that the extent of
repairs, as proposed by the Public Works Department, is proper
and necessary.
Now, Therefore, Be It Resolved that the following
appropriation is hereby approved:
FROM (Revenue) TO (Appropriation)
#80R (Water Fund Balance) $8 , 000 #24 (Maint. , Repair, Equip. ) $8 , 000
Adopted this a of 1979
• Mayor
ATTEST:
City Clerk
Reviewed for Administration:
City bf6nager
0
SUBJECT: SUMMARIES AND COST OF WELL #3 REPAIR
•
The project cost summary
Rig and Labor for Removing and Replacement $ 1491 .50
Repair Parts 7776.55
Shop Labor 882.00
Subtotal $10150.05
Motor Repair
Total
Repair Parts Required
1 ea Sandblast and paintbead shopman $ 21 .00
1 ea 1-11/16 x 65 inch long top special shaft 241 .00
1 ea Box 1-11/16 packing 8.25
1 ea V20 1-11/16 bushing 27.50
1 ea 10'' x 5' bottom columnpipe T.B.E 153.00
21 10'' x 10' columnpipe T.B.E. ($173 ea) 3633.00
28 1-11/16 rubber bearings ($14.25 ea) 399.00
6 10'' steel couplings ($95 ea) 570.00
• 21 1-11/16 sleeves ($23.80 ea) 499.80
6 1-11/16 x 10' line shafts ($124.50 ea) 747.00
1 1-11/16 x 5' line shaft 112.00
9 1-11/16'' couplings ($7 ea) 63.00
1 8' x10' suctionpipe 155.00
1 8'' Galy. cone strainer 95.00
1 1-11/16 stainless steel impeller shaft 290.00
7 Bowl bushings ($6 ea) 42.00
5 12'' RK over-size wearings ($125 ea) 625.00
5 Machinist to turn 12'' RK impeller shaft 116.00
($29 per hour -- 4 hours)
Total $ 7776. 55
Shop man -- 42 hours @ $21 Der hour S 882.00
The cost summary is to replace the necessary parts to put Well #3 back in
working order. When the pump was repaired in 1973, the pump was changed and it
was specified the cheapest pump that could be purchased and now we are experiencing
more repairs . I recommend that we replace the existing steel couplings and bronze
spiders with cast steel couplings. By doing this we will insure better service
of our pump and should be able to cut down on the wearing of parts in the future.
tWe need 21 10'' x 1-11/16'' combination couplings ($221 each -- $4651 ) . We
do have the option to rciace some of the steel coupling this time and the remainder
the next time we pull tiie pump.
I
-2-
We should paint all of the column pip to cut down on corrosion and try
to get longer life out of our columns. In 1973 we replaced all of the column
pipe and this time we have to replace 21 . The cost of sandblasting and painting
the columns is $65 per ten foot section. We should at least paint the sections
that are in the water, if we need an option.
If we do what I recommend, we will have a cost of about $17,211 .05.
1 budgeted $10,000. 1 need a decision as soon as possible so we can get the
well back in good working order.
Larry Hamer, Director
Public Works Department
LH:pjr
4-17-79
•
•