CITY OF ST. ANTHONY
RESOLUTION 93-028
A RESOLUTION AUTHORIZING THE SUBMITTAL OF A
GRANT APPLICATION TO THE METROPOLITAN WASTE
CONTROL COMMISSION FOR INFILTRATION/INFLOW
CONTROL PROJECTS
WHEREAS, the City of St. Anthony authorizes the submittal of a grant application to the
Metropolitan Waste Control Commission for an infiltration/inflow control project
to assist the City in its efforts to reduce infiltration and inflow into the sanitary
sewer system; and
WHEREAS, the application request is for$10,000, and the City of St. Anthony will match this
amount if awarded the grant; and
WHEREAS, the proposed project would create a low-interest loan fund for St. Anthony
residents to disconnect sump pumps and/or drain tile from the sanitary sewer
• system.
NOW, THEREFORE, BE IT RESOLVED, that the City Council of the City of St. Anthony
authorizes the submittal of a grant application to the Metropolitan Waste Control Commission
for an infiltration/inflow control project and designates Larry Hamer, Public Works Director,
as the subject matter contact.
Adopted this IT-11- day of eeLa,,iclj 1993.
i
Mayor
ATTEST:
City Clerk
Reviewed for administration:
City Manager
•
IW*
CITY OF ST. ANTHONY
PROPOSED INFILTRATION/INFLOW CONTROL PROJECT
•
DESCRIBE THE OBJECTIVE OF THE PROJECT:
With a $10,000 MWCC grant and $10,000 City matching contribution, a $20,000 low interest
loan pool would be created for homeowners (on a first-come, first-serve basis) to disconnect
sump pumps and drain tile from the sanitary sewer system.
MWCC provided data for St. Anthony waste water flows illustrates that the gallons per capita
per day (GPCPD) fluctuates with the amount of precipitation (see Attachment A). The data
suggests there is a significant amount of "clear water" from illegal sump pump/drain tile
connections to the sanitary sewer system. Additionally, St. Anthony, which was developed
mainly in the 1950s and 1960s, is a first-ring suburb of Minneapolis. A common home
construction practice at that time was the sump pump/drain tile connections to the sanitary sewer
system.
The benefit of an MWCC grant would allow the City of St. Anthony to create a low interest
loan pool to begin the process of disconnecting the illegal sump pump/drain tile connections to
the sanitary sewer system. The City has attempted to begin this process through a recently
adopted ordinance. The ordinance requires an inspection at the time of sale, where the
homeowner can be ordered to disconnect (see Attachment B). Approximately 40 to 50 homes
are sold each year in St. Anthony. There are approximately 2,400 households in St. Anthony.
The grant money would allow additional homes to be completed (40 homes with a $500 loan
• limit). The low-interest payback would replenish the loan pool and allow additional homes to
disconnect. Approximately two new homes per quarter could receive money. Over a period
of time, the situation will steadily be dealt with. In ten years, a potential of 512 homes could
disconnect (assuming all homes are connected). This includes homes disconnecting due to the
point of sale provision in the ordinance.
40 homes for sale * 10 years = 400 homes
40 homes receive $500 low interest loan = 40 homes
2 new homes per quarter times 4 quarters times 9 years = 72 homes
assuming five year payback -- $100 + interest/year -- quarterly payback of $25
+ interest times 40 homes is $1,000 = 2 new homes
The interest rate could be set at the rate of inflation -- 3% to 4%. This would allow the loan
pool to replenish for the long term. A loan would have the same interest rate for its term. The
interest rate could be adjusted for new loans using the Consumer Price Index.
PROPOSED SCHEDULE FOR PROJECT COMPLETION
Advertise so 40 homes in the City will take advantage of the program in the first year.
Hopefully, a waiting list will be established so incoming quarterly loan payments can be lent out.
The project will be administered by City staff. Actual disconnect work will be conducted by
• a contractor of the homeowner's choice. The City could provide a list of licensed and/or
recommended contractors. The City could also provide homeowners with information, so that
a contractor's quote is not out of line.