CITY OF ST. ANTHONY
RESOLUTION 02-040
A RESOLUTION A RESOLUTION APPROVING THE
CITY OF ST. ANTHONY 2002 GOALS
WHEREAS, goal setting sessions were held on January 24 and January 25, 2002 to establish
the City's goals for 2002; and
WHEREAS, attendees at the sessions were the Mayor and Councilmembers; City Manager and
City staff; the Chairs of the Planning Commission and Parks Commission and a
facilitator; and
WHEREAS, Jim Prosser, Ehlers &Associates, Inc., was the facilitator and he has submitted a
report on the results of the goal setting sessions.
• NOW,THEREFORE, BE IT RESOLVED that the City Council of the City of St. Anthony,
hereby approves the City's 2002 Goals as set forth in the attached report submitted by said
facilitator.
Adopted this Q 3 day ofr;AAr L , 2002.
Mayor
ATTEST:
City Clerk
Reviewed for Administration:
City Manager
•
CITY OF ST. ANTHONY
2002 GOALS
1 . Redevelop Apache Center Area Property.
2. Develop Public Facilities Plan:
a. Public Works facility
b. SAV #I
c. Stonehouse
d. Fire Station
3. Maintain legislative presence on critical
St. Anthony Issues.
4. Develop plan for long term financial needs.
5. Enhance community involvement in critical City
issues.
EHLERS
& ASSOCIATES INC
Target Completion Date
GOAL#1
Redevelop Apache Center Area Property 10/05
Target Completion Date
STRATEGY#1
Facilitate redevelopment through developer 10/05
DEFINE GOAL ACCOMPLISHMENT
Redevelopment completed for major portion of Apache Mall area
TARGET
PRIMARY KEY COMPLETION
ACTION STEPS RESPONSIBLE INDIVIDUALS DATE RESOURCES
1. Compile&execute redevelopment aeement EA EA/JG 04/23/02 2500
2. Identify alternate funding sources TG DSU/EA 04/15/03 1500 ?
3. Develop project timeline EA PT 5/15/03 500
4. Establish TIF District EA JG/PT 6/1/03 5000
5. Assess need for environmental study WSB DSU/PT 8/l/02 500
6. Identify property acquisition strategy PO PT/JG 08/15/02 -
7. Identify phasingoptions PO PT/DSU 08/15/02 -
8. Establish design guidelines/review/planning process DSU PO 04/15/03 TBD
9. Revise communication plan SH PG/JMS/HRA 5/28/03 TBD
10. Establish public participation plan DSU SH/EA/HRA 05/15/02 -
11. Complete development aeement EA JG 04/15/03 5000
12. Project oversight HRA Quarterly update
St.Anthony Village 2002 Strategic Plan
Ehlers&Associates
Pagel of 8
EHLEIS
& ASSOCIATES INC
Target Completion Date
GOAL#2
Develop Public Facilities Plan 4/03
Target Completion Date
STRATEGY#1
Prepare plan for upgrade or replacement of DPW facility 2/03
DEFINE GOAL ACCOMPLISHMENT
DPW building complete
TARGET
PRIMARY KEY COMPLETION
ACTION STEPS RESPONSIBLE INDIVIDUALS DATE RESOURCES
1. Review preliminary analysis on bldg needs/options MM JH/KA 4/2 CC MTG
2. Develop plan to communicate SH JMS/CC 7/01/02 500
needs/process/options/solutions.
3. Select project manager/architect/planning firm to assist CC MM/JH 8/1 CC MTG
with preparation of options.
4. Develop process to review options and develop TBD STAFF 10/1/02 500
recommendations.
5. Develop options to address DPW facility needs. TBD EA/STAFF 10/1/02 -
tions to include cost of financing alternatives.
6. Select options. CC STAFF 1/1/03 CC MTG
7. Determine funding source. CC STAFF/EA 11/01/02 CC MTG
8. Approve plan&specs. CC STAFF 02/01/03 $?/CC MTGCC MTG
9. Award contract for building. CC TBD/STAFF 04/01/03 -
St.Anthony Village 2002 Strategic Plan
Ehlers&Associates
Page 2 of 8
EHLERS
& ASSOCIATES INC
Target Completion
GOAL#2 Date
Develop Public Facilities Plan 2/03
Target Completion
STRATEGY#2 Date
Assess need and feasibility for replacement of SAV#1 12/02
DEFINE GOAL ACCOMPLISHMENT
Analysis of need and feasibility completed. Building completed if determined to be needed.
TARGET
PRIMARY KEY COMPLETION
ACTION STEPS RESPONSIBLE INDIVIDUALS DATE RESOURCES
1. Select contract manager/architect firm to assist with CC MMML/STAFF 8/01/02 CC MTG
design.
2. Identify potential alternate locations for SAV#1. ML MM/? 8/01/02 ?
3. Identify cost for land acquisition/building. ML MM/STAFF 8/01/02 -
4. Determine funding source. EA ML/MM 10/01/02 0
5. Negotiate land purchase. ML MM/JG 10/01/02 500
6. Approve plan and specs. CC ML/N1M 1/1/03 $?/CC MTG
7. Award contract for building. CC TBD 3/1/03 CC MTG
St.Anthony Village 2002 Strategic Plan
Ehlers&Associates
Page 3 of 8
EHLERS
& ASSOCIATES INC
Target Completion Date
GOAL#2
Develop Public Facilities Plan 2/03
Target Completion Date
STRATEGY#3
Prepare plan for future of Stonehouse 1/03
DEFINE GOAL ACCOMPLISHMENT
Charitable gambling secures alternate site.
TARGET
PRIMARY KEY COMPLETION
ACTION STEPS RESPONSIBLE INDIVIDUALS DATE RESOURCES
1. Meet with Charitable gambling to review future JD RH/MM/ML/EA 4/2/02 2000
options to Stonehouse.
2. Call for referendum. CC JG/MM/STAFF 06/01/02 CC MTG
3. Prepare/implement communication plan for split SH JMS 06/01/02 2500
liquor referendum.
4. Conduct referendum. CK CC 11/7/02 $?
5. Prepare ordinance regulating on sale liquor store. JG CC 12/01/02 500
6. Close Stonehouse CC ML/MM OPEN
St.Anthony Village 2002 Strategic Plan
Ehlers&Associates
Page 4 of 8
• s
EHLEPS
& ASSOCIATES INC
Target Completion
GOAL#2 Date
Develop Public Facilities Plan 2/03
Target Completion
STRATEGY#4 Date
Prepare plan for replacement of Fire Station 2/03
DEFINE GOAL ACCOMPLISHMENT
Fire station building completed
TARGET
PRIMARY KEY COMPLETION
ACTION STEPS RESPONSIBLE INDIVIDUALS DATE RESOURCES
1. Review preliminary analysis on bldg needs/options MM JH/KA 4/2 CC MTG
2. Develop plan to communicate SH JMS/CC 7/01/02 500
needs/process/options/solutions.
3. Select project manager/architect/planning firm to CC MM/JH 8/1 CC MTG
assist with preparation of options.
4. Develop process to review options and develop TBD STAFF 10/1/02 500
recommendations.
5. Develop options to address DPW facility needs. TBD EA/STAFF 10/1/02 -
tions to include cost of financing alternatives.
6. Select options. CC STAFF 1/1/03 CC MTG
7. Determine funding source. CC STAFF/EA 11/01/02 CC MTG
8. Approve plan& secs. CC ISTAFF 02/01/03 $?/CC MTGCC MTG
9. Award contract for building. CC TBD/STAFF 04/01/03 -
St.Anthony Village 2002 Strategic Plan
Ehlers&Associates
Page 5 of 8
EHLERS
& ASSOCIATES INC
Target Completion
GOAL#3 Date
Maintain legislative presence on critical St. Anthony issues 6/03
Target Completion
STRATEGY#1 Date
Communicate to legislators re: impact of various tax proposals; DNR funding; wine and beer sales in grocery stores; 6/03
funding for Apache
DEFINE GOAL ACCOMPLISHMENT
Resources required to complete redevelopment identified and secured.
TARGET
PRIMARY KEY COMPLETION
ACTION STEPS RESPONSIBLE INDIVIDUALS DATE RESOURCES
1. Meet with key legislators re issues RH/CC MM 06/01/02 -
2. Provide appropriate back ound materials MM CC 06/01/02 -
3. Meet with Met Council PT CC/MM Open -
4. Provide follow up report/mtg MM CC MTG
5. Communicate results to public SH -
St.Anthony Village 2002 Strategic Plan
Ehlers&Associates
Page 6 of 8
EHLERS
& ASSOCIATES INC
Target Completion Date
GOAL#4
Develop plan for I ng term financial needs. 6/02
Target Completion Date
STRATEGY#1
Complete KFS process 6/02
DEFINE GOAL ACCOMPLISB[MENT
Approval of 2002 Key Financial Strategies Plan by City Council
TARGET
PRIMARY KEY COMPLETION
ACTION STEPS RESPONSIBLE INDIVIDUALS DATE RESOURCES
1. Review projected capital and operating needs. (KFS EA CC/STAFF 04/23/02 CC WORKSHOP
#3) $3750
2. Identify and evaluate alternate strategies to meet EA CC/STAFF 04/23/02 CC WORKSHOP
financial needs S #3) -
3. Prepare plan and schedule timetable for EA CC/STAFF 8/3/02 CC WORKSHOP
implementation S#4 $3750
4. Update plan or part of budget process. MM STAFF/CC ONGOING
St.Anthony Village 2002 Strategic Plan
Ehlers&Associates
Page 7 of 8
EHLERS
& ASSOCIATES INC
Target Completion Date
GOAL#5
Enhance community involvement in critical city issues 12/02
Target Completion Date
STRATEGY#1
Develop structure for enhanced community involvement. 12/02
DEFINE GOAL ACCOMPLISHMENT
1.Implementation of communication plans for facility improvements, Apache redevelopment.
2.Completed website enhancement
3. Customer feedback program established for selected services.
TARGET
PRIMARY KEY COMPLETION
ACTION STEPS RESPONSIBLE INDIVIDUALS DATE RESOURCES
1. Develop customer service feedback for selected city MM STAFF 8/02 -
services
2. Improve website SH CK 12/02 $?
3. Improve cable access broadcast SH JH 12/02
4. Improve community understanding of role of SH MM/CC Ongoing TBD
Mayor and Council in policy making.
St.Anthony Village 2002 Strategic Plan
Ehlers&Associates
Page 8 of 8