Document: CC RES 98-021 RESOLUTION AUTHORIZING SUBMITTAL OF
METROPOLITAN COUNCIL ENVIRONMENTAL SERVICES LOAN
APPLICATION FOR AN INFILTRATION/INFLOW REDUCTION PROJECT
r
• CITY OF ST. ANTHONY
RESOLUTION 98-021
A RESOLUTION AUTHORIZING SUBMITTAL OF
METROPOLITAN COUNCIL ENVIRONMENTAL SERVICES
LOAN APPLICATION FOR AN INFILTRATION/INFLOW
REDUCTION PROJECT
WHEREAS, the Metropolitan Council Environmental Services (MCES) has established an
infiltration/inflow (I/I) reduction goal for the City of St. Anthony; and
WHEREAS, the City of St. Anthony desires to conduct a sump pump identification and
removal project to reduce the existing I/I in the sanitary sewer system; and
WHEREAS, the MCES has established a matching grant/loan program for qualifying I/I
reduction projects in the MCES tributary communities; and
WHEREAS, the proposed sump pump identification and removal project will qualify for the
MCES loan program for up to $40,000; and
WHEREAS, the loan repayment is conditional on the long term effectiveness of the I/I
• reduction project.
NOW, THEREFORE, BE IT RESOLVED that:
1. The City Manager is directed to submit a loan application to the MCES
for the sump pump identification and reduction project.
2. The City Manager is designated as the City of St. Anthony contact
person for the MCES Loan Program.
3. The City of St. Anthony will review the loan offer when received from
the MCES and enter into a formal agreement if deemed appropriate.
Adopted this 27 day of r!/ 1998.
4ayor
ATTEST:
City Clerk
• Reviewed for administration:
City na er
-
METROPOLITAN COUNCIL EN V IKL)iNrtIbLN I A1, aztc v l%•c.o
OFFER of MATCEaNG VQ FOR nGgLTRA1I0N/I1nWW CONTROL PROJECTS
LOAN AppLICATION FORM
NanCE'TO APP CANTS: Brad the attached"Metropolitan Council Favironmemtal Services=ddda -Description of Offer of
8 Loan acrd Grant monies to Com mnWes for InBltration/tallow Controls"for guidance on how
this Loan Offer will
bo=ducted. Prior to award of a Loan. the Applicant Community rust cater into an agrxm
ent with the MCES. 'Me
campletc terms of the agrement will be furnished to those Applicants to whom a Loan Offer is mads.
COMMUNITY NAME: Str►r►
Correspondence regarding this Application should be mailed to:
NAME: Mr.. Mike Wrnson
TITLE: City Manager - St. An ny
STREET: 1301 gilverLake nand
CITY,ZIP: St:. Anthony# M 55416-1699
LOAN AMOUNT REQUESTED FROM MCES: $ 40,000
(pater a value up to $40,000.00. An equal amount is required to be coptributed by the Community to be eligible
for a Loan).
I*VIDE THE FOLLOWING ON SEPARA'T'E SHEETS OF PAPER:
Describe the objectives of the project. Mghlight any benefits that the project is intended to provide to the
Metropolitan System of wastewater interceptor sewers and treatment plants. Does the project eliminate a
historic sanitary sewer bypass? If so provide WCA reporting form on incidence(s).
Provide a complete description ofthe proposed project. Include a map showing the limits of the project area and
the wastewater collection system in the vicinity of the project. You may attach any engineering reports, plans or
other pertinent do=-!,I I q that provide useful background for MCES evaluation of the proposed project.
What is the proposed schedule for the project completion, assuming a Loan is offered? If possr'ble, identify key
steps and intermediate dates. Would the project be performed by contracted services or by City staff? Will a
competitive bid process be required?
What is the estimated amount of V1.expected to be removed from system after completion of the project?
(MO Y) Provide basis of estimate.
Provide copy of official minutes of governing body which authorizes a li t to apply for loan
Print Name of Preparer Signa o reparreer
• Telephone Number:
Title of Preparers ` . ) � �Y)M
Date of Application:
APPUCATIONS MUST BE POSTMARt= NO THAN FEBRUARY 10, 1998. APPLICATIONS ,
WML BE REVMWgD AND OFFERS EXTENDED TO QUALUUD SUBMITTALS IN MARCH.
Supporting Information
City of St. Anthony
Sump Pump Identification and Removal Project
MCES Loan Application
• January 1998
Objectives
Project Benefits
Bypasses
Description of Proposed Project
Schedule for Completion
Attachments:
Ordinance 1993-OOA(Draft)
Sanitary Sewer System Map
Sample Inspection Form
Sample Notification Cards
•
• Ob' tives
The objective of the proposed project is to eliminate the sump pump-based infiltration and
inflow in the City's waste water collection system.
Project Benefits
Sump pumps have been documented to contribute significant peak flows and long term
quantities of 1/1 during extended wet weather periods. Removal of sump pumps will provide
an immediate reduction in peak flows and the long term wet weather.flows. Peak reduction
is a benefit to the City by reducing the potential for system backups or the need to increase
pipe sizes due to high flow rates.
The MCES system would experience similar benefits of reduced demands on interceptor
sewers,pumping stations and treatment facilities.
Reduction of the long term 1/1 will be a benefit to the City through reduced operation and
maintenance costs for lift station and reduced treatment changes paid to the MCES. The
MCES will receive similar,benefits in reduced operation and maintenance costs of lift
stations and treatment facilities. Metro wide benefit would be realized due to the additional
• capacity made available at the treatment facility.
A review of the waste water flow records and discussions with local officials suggests that
there may be two hundred(200)sump pumps in the city that may be identified and removed
through this project. During an extremely wet year like 1996, removal of the sump pump
connections may reduce annual 1/1 flows by about 15%or 16 million gallons per year. These
estimates are based on several assumptions which will b investigated and documented as part
of the project. Upon completion of the survey project it will be possible to more accurately
predict 19 reduction potential.
Bypasses
The City of St. Anthony has not been required to bypass from the waste water collection
system. However, during the July 1997 high flow period approximately 50 - 75 homes
reported backups of waste water into their basements and many more backups may not have
been reported.
Description of Proposed Project
The proposed project is designed to identify and remove sump pump connections to the
sanitary sewer. The project will include public information,physical survey of each home
(building) in the City, and follow-up survey to verify removal of sump pump connections.
•
The first step in the project is the adoption of an ordinance requiring inspection and removal
with penalties for noncompliance. The City is currently working on this phase and the
ordinance should be adopted in February 1998. A copy of the draft ordinance is attached.
VQ 1 1- L 1 -J�/ V L • V.....
• The next stepwill be an extended public information program to develop support for the
planned sump pump disconnection work. information on the new ordinance and planned
inspection program will be published in the spring and summer City newsletters. In addition,
the City will prepare a short video program for airing on the cable television system. The
video will also be used for the planned public information meetings.
The initial public information effort will be followed by neighborhood meetings to introduce
the actual sump pump inspection effort. There are approximately 2,300 connections in the
City of St.Anthony. The City will be divided into four roughly equal study areas to provide
manageable areas for evaluation. The inspection approach in each study area will be similar.
To begin the inspection process, a letter will be mailed to each homebuilding in the study
area. The letter will inform the resident of the ordinance provisions, discuss the City's
concern with the 1/I, indicate that an "inspector" will be coming to their home, and invite
them to a public information meeting. The letters will be mailed two to three weeks prior
to the meeting. At the public information meeting, brochures will be available with
information on sump pumps and recommended discharge methods, and City Staff will be
available to respond to questions from homeowners. After the information meeting, the
individual inspections will occur. Inspectors will visit each property and observe the
plumbing system to determine the presence or absence of a sump pump. Questions will be
• asked concerning foundation drainage tile but it is not possible to visually identify direct
drain tile connections with this limited survey.
If there is no sump pump or sump basket in the building,it will be accepted as"passing"the
inspection and an inspection form will be completed and left with the homeowner to verify
that the inspection was made and the pass/fail condition was communicated to the
homeowner. If the home has a correctly installed sump pump with an outside discharge,the
structure would also "pass"this inspection. If the home has a sump basket but no pump it
may "pass" the inspection,but a sticker will be placed on the cover of the basket informing
the resident of the need to obtain a permit for installation of the pump or be subject to the
potential fine of$100 per month.
If the house has a sump pump which does not comply with the ordinance provisions, the
building would "fail' the inspection and the inspector will inform the homeowner of the
improvements required to comply with the ordinance, In this case, a copy of the "failed"
survey form would be left with the homeowner and a second appointment would be made
for 30 days in the future. During this 30-day period, the property owner will have the
opportunity to correct the situation. After correction, the property will be reinspected to
verify compliance and provide the homeowner with a completed survey form indicating a
"passing" condition.
• The neighborhood meeting for the first study area is planned for October 1998, and the
majority of the inspections and corrections should be completed by late spring 1999.
Attached is a map of the St. Anthony sanitary sewer system. The project will include the
entire community. Also,attached are copies of the draft inspection forms and notification
cards that will be used in the inspection process.
• CO[n ICUOn
Schedule for
The preliminary schedule for completion of the proposed project is as follows:
Study Area 1 -Public Meeting October 1999
Inspections±575 Buildings November 1998
Study Area 2 _Public Meeting January 1994
Inspections±575 Buildings February 1999
Study Area 3 -Public Meeting February 1999
inspections±575 Buildings March 1999
Study Area 4 -Public Meeting March 1999
Inspections±575 Buildings April 1999
Complete±99%of Inspections June 1999
Su nmary Report July 1999
•