HomeMy WebLinkAboutCC RES 98-043 RESOLUTION RECEIVING AN ENGINEERING REPORT AND AUTHORIZING FOR BIDS RELATING TO REHABILITATION AND RECOATING OF AN ELEVATED WATER STORAGE TANK Meeting Sheet
IIIIIIVIIIVIIIVIIIVIIIVIIIIIIIIIII
103165
BOX: 26
Folder: RES 1998
Document: CC RES 98-043 RESOLUTION RECEIVING AN ENGINEERING
REPORT AND AUTHORIZING FOR BIDS RELATING TO REHABILITATION
AND RECOATING OF AN ELEVATED WATER STORAGE TANK
•
CITY OF ST. ANTHONY
RESOLUTION 98-043
A RESOLUTION RECEIVING AN ENGINEERING REPORT
AND AUTHORIZING A CALL FOR BIDS RELATING TO
REHABILITATION AND RECOATING OF AN ELEVATED
WATER STORAGE TANK
WHEREAS, following direction from the St. Anthony City Council, an engineering report
was prepared and submitted by Rieke Carroll Muller Associates, Inc. relating to
the feasibility of rehabilitating and recoating the City's existing elevated water
storage tank.
NOW, THEREFORE, BE IT RESOLVED, that the City Council of the City of St. Anthony
hereby authorizes the rehabilitation and recoating of the existing elevated water storage tank as
presented in the report by Rieke Carroll Muller Associates, Inc. and authorizes the
advertisement for bids for the project.
• Adopted this l o? day of l�/L�l , 1998.
Mayor
ATTEST:
City Clerk
Reviewed for administration.
City ger
•
• February 18, 1998
Mr. Mike Morrison
City of St. Anthony
3301 Silver Lake Road
St. Anthony,MN 55418-1699
Re: Proposal for Engineering Services
Recoating of Elevated Water Storage Tank
St. Anthony,MN
RCM File No. 10456.00
Dear Mr. Morrison:
Rieke Carroll Muller Associates, Inc. (RCM) appreciates the opportunity to provide the City
of St.Anthony with this proposal to prepare an engineering report which will identify the scope
of work needed to rehabilitate and recoat the City's elevated water storage tank. Preparation of
the report will include collection,review and analysis of available information as well as a site
survey of the present coating system and structure to determine their condition. The site survey
Ic I]] will be a visual inspection both inside and outside the tank and samples of the existing coating
system will be collected so that we can identify the proper preparation work and develop the
carrdata necessary for specifying a compatible coating system. The report will also include
Carroll �' p �g p g Y p
muller estimated construction costs for the project,including welding and miscellaneous repairs.
wociates, inc.
gineers
architects Once the report has been completed by RCM and approved by the City,project specifications
land surveyors can be prepared to encompass the repairs and recoating details identified in the report.
equal opportunity
employer RCM proposes to provide this report to the City of St. Anthony for a lump sum fee of$4,800,
including expenses.
RCM understands that the City intends to have its new logo painted on the tower. Recognizing
that the new logo is a different color from the old one,it may be necessary to change the base
color of the tower to more closely complement the color of the new logo. RCM recommends that
the City select a color combination and logo placement scheme to be used with the tower
recoating. To assist the City with its selection process,we can provide a representative color
palette and a schematic representation of the tower with the new logo.
years Please call us if you have questions.
helpingof
build Sincerely,
communities
RIEKE CARROLL MULL ASSOCIATES,INC.
l
L/
chard C. Potz Har(y Koutsoumbos,P.E.
innetonka,
01 red circle dr. Project Manager Vice President
t office box 130
mn
55343-0130
(612)935-6901 ma L. laassen,P.E.
fax(612)935-8814 President/CEO
www.rcm-assoc.com