HomeMy WebLinkAboutHRA MINUTES 03081988n
U
C 2 TY O F S T. ANT HOINT Y
HOU S T N G AN D R E D EV E L O PMENT
AUTHOR 2 TY M= N UT E S
MAR C H 8, 1 9 8 8
1 The meeting was called to order at 9:20 P.M. by Chair Sundland.
2 Present for roll call: Sundland, Vice Chair Enrooth, Secretary/
3 Treasurer Marks, and Commissioners Makowske
4 and Ranallo.
5 Also present: David Childs, Executive Director
6 William Soth, H.R.A. Attorney
7 FEBRUARY 24, 1988 H.R.A. MINUTES
8 Motion by Marks, seconded by Ranallo to approve as presented.
9 Motion carried unanimously.
10 CLAIMS
11 Motion by Ranallo, seconded by Enrooth to approve payment of $146.25
12 to the Dorsey & Whitney law firm for legal services rendered the
013 H.R.A. in January, 1988, having to do with final development of the
14 Kenzie Terrace Redevelopment project.
15 Motion carried unanimously.
16 STAFF UPDATE ON KENZIE TERRACE REDEVELOPMENT PROJECT - CHILDS AND SOTH
17 Childs reported:
18 *Gaughan had consented to putting up $20,000 which Lang/Nelson
19 surpassed by agreeing to the $40,000 the H.R.A. had said it
20 needed as a guaranty the project would be finished;
21 *he and Mr. Soth had not been quite ready to recommend accept -
22 ance of the latter without first telling the H.R.A. what Lang/
23 Nelson's contingencies would be for doing that;
24 *they would be meeting with Lang/Nelson the rest of the week and
25 it was very possible the differences might be worked out by
26 the middle of next week so the H.R.A. could hold a special
27 meeting where either Gaughan or Lang/Nelson would hopefully
28 present the $360,000 Letter of Credit as well as either the
29 $20,000 or $40,000 option payment and sign the Redevelopers
30 Agreement;
31 *he was not yet sure which would happen since both developers
•32 seem to want to do the project.
•I In relation to the Lang/Nelson talks, the Executive Director said the
2 negotiator, Mr. Brewer, had brought in a conditional commitment from
3 Juran and Moody to finance the project, which he perceived Lang/Nelson
4 and the financing firm hadn't yet negotiated fully. He added that
5 those negotiations couldn't be completed until the next Monday when
6 all the Juran and Moody people would be back from Hawaii. So, of
7 course, the Lang/Nelson negotiator was reluctant to hand over the
8 $40,000 check before those negotiations were finalized.
9 Soth reported one thing Lang/Nelson had said they were prepared to do
10 was to put $40,000 at risk if they were designated as the project
11 developers. However, because of the uncertainties surrounding the
12 financer's contingencies, he and Mr. Childs had been reluctant to make
13 a firm recommendation to the H.R.A. before next Monday.
14 Childs indicated another issue he perceived the H.R.A. should
15 consider was the possibility that Lang/Nelson might want to construct
16 three buildings, which would change the building footprints a bit and
17 leave less green space, but would permit the developers to enlarge
18 the unit size to meet what they perceive to be the market demand. He
19 said it would be up to the H.R.A. and Planning Commission to interpret
20 how significant those changes were when it came to deciding whether
21 public hearings were necessary, but added whatever number of
22 buildings there were, Lang/Nelson would be doing the project all at
23 one time.
•24 2
Ranallo restated his opinion that $20,000 difference between the two
5 offers wasn't that much money and he thought the City should stay
26 with Gaughan whose plan he liked best.
27 Soth told him he would have been a lot more comfortable with
28 designating Gaughan as developer if they had come right out and
29 indicated they intended to do the project and were only waiting to
30 find out what they had to do to get it done, rather than indicating
31 they wanted to get "everything" and telling the negotiators it was
32 O.K. with them if they found another developer.
33 Sundland agreed that Gaughan had not kept their original promise to
34 the H.R.A. to sign the agreement first and "button down" the details
35 later.
36 Childs indicated, on the other hand, that he knew from financial
37 people Gaughan was negotiating with, that the developer was working
38 hard trying to get financing. He also said the Gaughan architect had
39 told him he was working on different plans for the project every day
40 that the developer was talking to financial institutions to try to get
41 backing.. He added that there were people looking at the project for
42 both developers every day and perceived it would be better for the
43 next five days to let both keep on working to get the best financing
44 deal they can. The Manager told Mr. Soth he had gotten a call from
45 Paul Brewer of Lang/Nelson after he had talked to the attorney, which
is
2
•1 indicated they wanted to work on the Redevelopment Agreement this week
2 so they wouldn't have to waste time on it next week.
3 Soth told Commissioner Ranallo that considering there would still be
4 200 units in the project, public hearings on Lang/Nelson's changes
5 might not be necessary, depending on how significant those changes
6 might be.
7 Childs indicated the developers perceived they needed the extra 100-
8 200 square feet per unit to be successful in marketing the project,
9 which the Vice Chair indicated from a marketing perspective , he
10 couldn't argue with.
11 Makowske agreed larger units might be better for the project:
12 ADJOURNMENT
13 Motion by Ranallo, seconded by Marks to adjourn the H.R.A. meeting at
14 9:35 P,.M. for an informal discussion of timetables for Executive
15 Sessions relative to the water contamination litigation.
17 Respectfully submitted,
018 Helen Crowe, Secretary