HomeMy WebLinkAboutRES 16-067 AWARDING A BID FOR THE ADVANCED OXIDATION PROCESS WATER TREATMENT PLANT AND APPURTENANT WORK INCLUDING THE REHABILITATION OF THE GROUND STORAGE RESERVOIRCITY OF ST. ANTHONY VILLAGE
STATE OF MINNESOTA
RESOLUTION 16 -067
A RESOLUTION AWARDING A BID FOR THE
ADVANCED OXIDATION PROCESS WATER TREATMENT PLANT
AND APPURTENANT WORK INCLUDING THE REHABILITATION
OF THE GROUND STORAGE RESERVOIR
WHEREAS, pursuant to an advertisement for bids for the improvement as shown on the plan for the
above - referenced project, bids were received, opened and tabulated according to law, and the
following bids were received complying with the advertisement:
Contractor Total Bid
Gridor Construction, Inc. $6,614,700.00
Rice Lake Construction Group $6,652,700.00
Municipal Builders, Inc. $6,704,500.00
WHEREAS, it appears that Gridor Construction, Inc. of Buffalo, MN is the lowest responsible bidder,
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of St. Anthony Village that:
1. The Mayor and City Manager are hereby authorized and directed to enter into a contract
with Gridor Construction, Inc. in the amount of $6,614,700.00 in the name of the City of
St. Anthony Village, Minnesota for the improvement outlined in the above - referenced
project according to the plans and specifications, therefore, approved by the City
Council and on file in the office of the City Clerk.
2. The Engineer, WSB & Associates, Inc., is hereby authorized and directed to return
forthwith to all bidders the deposits made with their bids, except that the deposits of the
successful bidder and the next two lowest bidders shall be retained until a contract has
been signed.
Adopted this 13"' day of September, 2016.
ATTEST:
Nicol Miller, City Cle •k
Reviewed for administration:
Jerome O. Faust, Mayor
404
Mark Casey, Cit anager