Laserfiche WebLink
The Geronimo Development Process <br />SITE CONTROL <br />Identify flat land with adjacent access to robust 3 -Phase distribution level electrical service <br />INTERCONNECTION ANALYSIS <br />ERONW40 <br />ENERGY <br />® Research substation loading, transformer size and distance to substation in order to determine optimal <br />project size <br />PUBLIC RELATIONS <br />• Establish community relationships and local support <br />LAND USE PERMITTING <br />• Obtain land use permit (Conditional Use Permit, Interim Use Permit) <br />ENGINEERING AND ENVIRONMENTAL PERMITTING <br />Conduct studies for permitting and construction including: Alta survey, wetlands and storm -;mater, <br />phase 1 report, geotech borings, archeological field work <br />Proprietary and Confidential <br />www.geronimoenergy.com <br />12 <br />