30" RADIUS MULCH RING
<br />1.SXA
<br />MIN.
<br />UNDISTURBED
<br />SUBGRADE 1
<br />1
<br />aim
<br />DIG PLANTING PIT 4" TO 6"
<br />DEEPER THAN ROOT BALL
<br />NOTE:
<br />CONTRACTOR SHALL MAINTAIN TREES IN A PLUMB
<br />POSITION THROUGHOUTTHE WARRANTY PERIOD. IF
<br />STAKING IS REQUIRED BY SITE CONDITIONS,
<br />CONTRACTOR TO USE 2 OR 3 STAKE METHOD WITH 1"
<br />WEBBING AROUND TRUNK OF TREE (NO WIRE OR
<br />CABLING TO BE USED)
<br />WRAP TREE TRUNKS PER NOTES.
<br />PROVIDE & INSTALL RODENT PROTECTION
<br />1/2" HARDWIRE CLOTH, MESH CYLINDER, 8" DIA OR
<br />GREATER X 24" HT.. STAKE IN PLACE
<br />INSTALL TREE WITH ROOT FLARE VISIBLE AT TOP OF
<br />THE ROOT BALL. REMOVE SOIL IN LEVEL MANNER FROM
<br />TOP OF ROOT BALLTO EXPOSE 1ST 1/2" OR LARGER MAIN
<br />ORDER ROOT IF NEEDED. SET ROOT BALL WITH MAIN
<br />ORDER ROOT 1" ABOVE ADJACENT GRADE. DO NOT
<br />COVER TOP OF ROOT BALL WITH SOIL.
<br />INSTALL 3" LAYER OF SHREDDED HARDWOOD MULCH.
<br />PLACE NO MULCH IN CONTACT WITH TREE TRUNK
<br />REMOVE BURLAP, TWINE, ROPE AND WIRE FROM
<br />TOP HALF OF ROOT BALL
<br />BUILD 4" HIGH EARTH SAUCER BEYOND EDGE OF
<br />ROOT BALL
<br />- EDGE CONDITION VARIES
<br />PLACE ROOT BALL ON UNDISTURBED OR
<br />COMPACTED SOIL
<br />_ SCARIFY SIDES OF TREE PIT WITH SPADE BY HAND
<br />TO BIND WITH PREPARED SOIL
<br />- PLANTING SOIL, REFER TO SPECIFICATIONS, COMPACT TO 85%
<br />OF MAX. DRY UNIT WEIGHT ACCORDING TO ASTM D 698
<br />TAMP SOIL AROUND ROOT BALL BASE FIRMLY WITH FOOT
<br />PRESSURE SO THAT ROOT BALL DOES NOT SHIFT
<br />TREE PLANTING DETAIL
<br />1/4" = 1'-0"
<br />ROCK MULCH
<br />1" = 1'-0"
<br />Sep 27, 2019 - 2:57pm - User:afeldberg L:\PROJECTS\21797\CAD\Civil\Sheets\21797-Ll-LSCP.dwg
<br />ANUJI /irL KU( -K - JLL IVU I L_')
<br />:OMMERCIAL WEED BARRIER
<br />INISH GRADE - SLOPE TO DRAIN
<br />EDGER
<br />=D4RFr1 CI IRl-.RAr1F
<br />2'
<br />L1.02
<br />INSTALL 3" LAYER OF MULCH, DO NOT PLACE IN
<br />CONTACT W/ SHRUB STEM
<br />APPLY PRE -EMERGENT HERBICIDE
<br />EDGE CONDITION VARIES
<br />EDGER, REFER TO PLAN AND SPECIFICATION
<br />LOOSEN ROOTS OF CONTAINER GROWN PLANTS
<br />EXCAVATE PLANT BED MIN. 4" DEEPER THAN
<br />ROOT BALL HT.
<br />SCARIFY SIDES AND BOTTOM OF PLANTING BED
<br />WITH SPADE
<br />PLANTING SOIL. REFER TO SPECIFICATIONS
<br />UNDISTURBED SUBGRADE
<br />SHRUB PLANTING DETAIL
<br />3/8" = V-0
<br />PREPARE SOIL FOR
<br />- it rn nr -
<br />NOTE:
<br />REFER TO EXTERIOR PLANTING SPECIFICATION
<br />INSTALL 3" LAYER OF MULCH. DO NOT
<br />PLACE IN CONTACT WITH PLANT
<br />EDGE CONDITION VARIES
<br />EDGER, REFER TO PLAN AND SPECIFICATION
<br />LOOSEN ROOTS OF CONTAINER GROWN PLANTS
<br />PLANTING SOIL, REFER TO SPECIFICATIONS
<br />SCARIFY SIDES AND BOTTOM OF PLANTING BED WITH SPADE
<br />UNDISTURBED SUBGRADE
<br />PERENNIAL PLANTING DETAIL
<br />1/2" = 114
<br />NOTES
<br />K A I i i r I i
<br />STEEL EDGER
<br />1 1/2" = V-0"
<br />GENERAL NOTES:
<br />1. THE CONTRACTOR SHALL INSPECT THE SITE AND BECOME FAMILIAR WITH THE EXISTING
<br />CONDITIONS RELATING TO THE NATURE AND SCOPE OF THE WORK.
<br />2. THE CONTRACTOR SHALL VERIFY PLAN LAYOUT AND BRING TO THE ATTENTION OF THE LANDSCAPE
<br />ARCHITECT DISCREPANCIES WHICH MAY COMPROMISE THE DESIGN OR INTENT OF THE LAYOUT.
<br />3. THE CONTRACTOR SHALL BE RESPONSIBLE FOR COMPLYING WITH ALL APPLICABLE CODES,
<br />REGULATIONS, AND PERMITS GOVERNING THE WORK.
<br />4. THE CONTRACTOR SHALL PROTECT EXISTING ROADS, CURBS/GUTTERS, TRAILS, TREES, LAWNS AND
<br />SITE ELEMENTS DURING CONSTRUCTION. DAMAGE TO SAME SHALL BE REPAIRED AND/OR
<br />REPLACED AT NO ADDITIONAL COST TO THE OWNER.
<br />5. LOCATE AND VERIFY ALL UTILITIES, INCLUDING IRRIGATION LINES, WITH THE OWNER FOR
<br />PROPRIETARY UTILITIES AND GOPHER STATE ONE CALL 48 HOURS BEFORE DIGGING. CONTRACTOR
<br />SHALL BE RESPONSIBLE FOR THE PROTECTION AND REPAIR OF ANY DAMAGES TO SAME. NOTIFY
<br />THE LANDSCAPE ARCHITECT OF ANY CONFLICTS TO FACILITATE PLANT RELOCATION.
<br />6. THE LANDSCAPE CONTRACTOR SHALL COORDINATE THE PHASES OF CONSTRUCTION AND
<br />PLANTING INSTALLATION WITH OTHER CONTRACTORS WORKING ON SITE.
<br />7. THE CONTRACTOR SHALL REVIEW THE SITE FOR DEFICIENCIES IN SITE CONDITIONS WHICH MIGHT
<br />NEGATIVELY AFFECT PLANT ESTABLISHMENT, SURVIVAL OR WARRANTY. UNDESIRABLE SITE
<br />CONDITIONS SHALL BE BROUGHT TO THE ATTENTION OF THE LANDSCAPE ARCHITECT PRIOR TO
<br />BEGINNING OF WORK.
<br />8. THE PLAN TAKES PRECEDENCE OVER THE LANDSCAPE LEGEND IF DISCREPANCIES EXIST.
<br />QUANTITIES SHOWN IN THE PLANTING SCHEDULE ARE FOR THE CONTRACTOR'S CONVENIENCE.
<br />CONTRACTOR TO VERIFY QUANTITIES SHOWN ON THE PLAN.
<br />9. THE SPECIFICATIONS TAKE PRECEDENCE OVER THE PLANTING NOTES AND GENERAL NOTES.
<br />10. EXISTING TREES AND SHRUBS TO REMAIN SHALL BE PROTECTED TO THE DRIP LINE FROM ALL
<br />CONSTRUCTION TRAFFIC, STORAGE OF MATERIALS ETC. WITH 4' HT. ORANGE PLASTIC SAFETY
<br />FENCING ADEQUATELY SUPPORTED BY STEEL FENCE POSTS 6' O.C. MAXIMUM SPACING.
<br />11. LONG-TERM STORAGE OF MATERIALS OR SUPPLIES ON-SITE WILL NOT BE ALLOWED.
<br />12. CONTRACTOR SHALL REQUEST IN WRITING, A FINAL ACCEPTANCE INSPECTION.
<br />PLANTING NOTES:
<br />1. NO PLANTS SHALL BE INSTALLED UNTIL FINAL GRADING AND CONSTRUCTION HAS BEEN
<br />COMPLETED IN THE IMMEDIATE AREA.
<br />2. A GRANULAR PRE -EMERGENT HERBICIDE SHALL BE APPLIED TO ALL PLANT BEDS AT THE
<br />MANUFACTURERS RECOMMENDED RATE PRIOR TO PLANT INSTALLATION.
<br />3. ALL PLANTING STOCK SHALL CONFORM TO THE "AMERICAN STANDARD FOR NURSERY STOCK,"
<br />ANSI -Z60, LATEST EDITION, OF THE AMERICAN ASSOCIATION OF NURSERYMEN, INC. AND SHALL
<br />CONSTITUTE MINIMUM QUALITY REQUIREMENTS FOR PLANT MATERIALS.
<br />4. OVERSTORY TREES SHALL BEGIN BRANCHING NO LOWER THAN 6' ABOVE PAVED SURFACES.
<br />5. ALL PLANTS MUST BE HEALTHY, VIGOROUS MATERIAL, FREE OF PESTS AND DISEASE AND BE
<br />CONTAINER GROWN OR BALLED AND BURLAPPED AS INDICATED IN THE LANDSCAPE LEGEND.
<br />6. PLANT MATERIALS TO BE INSTALLED PER PLANTING DETAILS.
<br />7. ALL TREES MUST BE STRAIGHT TRUNKED AND FULL HEADED AND MEET ALL REQUIREMENTS
<br />SPECIFIED.
<br />8. THE LANDSCAPE ARCHITECT RESERVES THE RIGHT TO REJECT ANY PLANTS WHICH ARE DEEMED
<br />UNSATISFACTORY BEFORE, DURING, OR AFTER INSTALLATION.
<br />9. NO SUBSTITUTIONS OF PLANT MATERIAL SHALL BE ACCEPTED UNLESS APPROVED IN WRITING BY
<br />THE LANDSCAPE ARCHITECT.
<br />10. ALL PLANT MATERIAL QUANTITIES, SHAPES OF BEDS AND LOCATIONS SHOWN ARE APPROXIMATE.
<br />CONTRACTOR SHALL BE RESPONSIBLE FOR COMPLETE COVERAGE OF ALL PLANTING BEDS AT
<br />SPACING SHOWN AND ADJUSTED TO CONFORM TO THE EXACT CONDITIONS OF THE SITE. THE
<br />LANDSCAPE ARCHITECT SHALL APPROVE THE STAKING LOCATION OF ALL PLANT MATERIALS PRIOR
<br />TO INSTALLATION.
<br />11. ALL PLANTING AREAS MUST BE COMPLETELY MULCHED AS SPECIFIED.
<br />12. MULCH: SHREDDED HARDWOOD MULCH, CLEAN AND FREE OF NOXIOUS WEEDS OR OTHER
<br />DELETERIOUS MATERIAL, IN ALL MASS PLANTING BEDS AND FOR TREES, UNLESS INDICATED AS
<br />ROCK MULCH ON DRAWINGS. SUBMIT SAMPLE TO LANDSCAPE ARCHITECT PRIOR TO DELIVERY
<br />ON-SITE FOR APPROVAL. DELIVER MULCH ON DAY OF INSTALLATION. USE 3" FOR SHRUB BEDS,
<br />TREE RINGS, AND 3" FOR PERENNIAL/GROUND COVER BEDS, UNLESS OTHERWISE DIRECTED.
<br />13. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL MULCHES AND PLANTING SOIL QUANTITIES TO
<br />COMPLETE THE WORK SHOWN ON THE PLAN.
<br />14. USE ANTI -DESICCANT (WILTPRUF OR APPROVED EQUAL) ON DECIDUOUS PLANTS MOVED IN LEAF
<br />AND FOR EVERGREENS MOVED ANYTIME. APPLY AS PER MANUFACTURER'S INSTRUCTION. ALL
<br />EVERGREENS SHALL BE SPRAYED IN THE LATE FALL FOR WINTER PROTECTION DURING WARRANTY
<br />PERIOD.
<br />15. WRAP ALL SMOOTH -BARKED DECIDUOUS TREES PLANTED IN THE FALL PRIOR TO DECEMBER 1 AND
<br />REMOVE WRAPPING AFTER MAY 1. TREE WRAPPING MATERIAL SHALL BE WHITE TWO -WALLED
<br />PLASTIC SHEETING APPLIED FROM TRUNK FLARE TO THE FIRST BRANCH.
<br />16. ALL DECIDUOUS, PINE, AND LARCH PLANTINGS SHALL RECEIVE RODENT PROTECTION PER MNDOT
<br />2571.31.2
<br />17. PLANTING SOIL FOR TREES, SHRUBS AND GROUND COVERS: FERTILE FRIABLE LOAM
<br />CONTAINING A LIBERAL AMOUNT (4% MIN.) OF HUMUS AND CAPABLE OF SUSTAINING
<br />VIGOROUS PLANT GROWTH. IT SHALL COMPLY WITH MNDOT SPECIFICATION 3877 TYPE B
<br />SELECT TOPSOIL. MIXTURE SHALL BE FREE FROM HARDPACK SUBSOIL, STONES,
<br />CHEMICALS, NOXIOUS WEEDS, ETC. SOIL MIXTURE SHALL HAVE A PH BETWEEN 6.1 AND 7.5
<br />AND 10-0-10 FERTILIZER AT THE RATE OF 3 POUNDS PER CUBIC YARD. IN PLANTING BEDS
<br />INCORPORATE THIS MIXTURE THROUGHOUT THE ENTIRE BED IN A 6" LAYER AND
<br />ROTO -TILLING IT INTO THE TOP 12" OF SOIL AT A 1:1 RATIO.ANY PLANT STOCK NOT PLANTED
<br />ON DAY OF DELIVERY SHALL BE HEELED IN AND WATERED UNTIL INSTALLATION. PLANTS NOT
<br />MAINTAINED IN THIS MANNER WILL BE REJECTED.
<br />18. CONTRACTOR SHALL BE RESPONSIBLE TO VERIFY THAT EACH EXCAVATED TREE AND SHRUB PIT
<br />WILL PERCOLATE PRIOR TO INSTALLING PLANTING MEDIUM AND PLANTS. THE CONTRACTOR
<br />SHALL FILL THE BOTTOM OF SELECTED HOLES WITH SIX INCHES OF WATER AND CONFIRM THAT
<br />THIS WATER WILL PERCOLATE WITHIN A 24-HOUR PERIOD. IF THE SOIL AT A GIVEN AREA DOES
<br />NOT DRAIN PROPERLY, A PVC DRAIN OR GRAVEL SUMP SHALL BE INSTALLED OR THE PLANTING
<br />SHALL BE RELOCATED IF DIRECTED BY THE LANDSCAPE ARCHITECT.
<br />19. ALL PLANTS SHALL BE GUARANTEED FOR TWO COMPLETE GROWING SEASONS (APRIL 1 -
<br />NOVEMBER 1), UNLESS OTHERWISE SPECIFIED. THE GUARANTEE SHALL COVER THE FULL COST OF
<br />REPLACEMENT INCLUDING LABOR AND PLANTS.
<br />20. CONTRACTOR SHALL NOTIFY THE LANDSCAPE ARCHITECT AT LEAST 3 DAYS PRIOR TO PLANNED
<br />EEL EDGER (BLACK) W/ STAKE
<br />FINISHED GRADE AND EDGE
<br />CONDITION VARIES - SEE PLAN
<br />DELIVERY. THE CONTRACTOR SHALL NOTIFY THE LANDSCAPE ARCHITECT AT LEAST 24 HOURS IN
<br />ADVANCE OF BEGINNING PLANT INSTALLATION.
<br />21. SEASONS/TIME OF PLANTING AND SEEDING: NOTE: THE CONTRACTOR MAY ELECTTO PLANT IN
<br />OFF-SEASONS ENTIRELY AT HIS/HER RISK.
<br />21.1. POTTED PLANTS: 4/1 - 6/1; 9/21 - 11/1
<br />21.2. DECIDUOUS /B&B: 4/1 - 6/1; 9/21 - 11/1
<br />21.3. EVERGREEN POTTED PLANTS: 4/1 - 6/1; 9/21-11/1
<br />21.4. EVERGREEN B&B: 4/1 - 5/1; 9/21 - 11/1
<br />21.5. TURF/LAWN SEEDING: 4/1 - 6/1; 7/20 - 9/20
<br />21.6. NATIVE MIX SEEDING: 4/15 - 7/20; 9/20-10/20
<br />22. MAINTENANCE SHALL BEGIN IMMEDIATELY AFTER EACH PORTION OF THE WORK IS IN PLACE.
<br />PLANT MATERIAL SHALL BE PROTECTED AND MAINTAINED UNTIL THE INSTALLATION OF THE
<br />PLANTS IS COMPLETE, INSPECTION HAS BEEN MADE, AND PLANTINGS ARE ACCEPTED EXCLUSIVE
<br />OF THE GUARANTEE. MAINTENANCE SHALL INCLUDE WATERING, CULTIVATING, MULCHING,
<br />REMOVAL OF DEAD MATERIALS, RE -SETTING PLANTS TO PROPER GRADE AND KEEPING PLANTS IN
<br />A PLUMB POSITION. AFTER ACCEPTANCE, THE OWNER SHALL ASSUME MAINTENANCE
<br />RESPONSIBILITIES. HOWEVER, THE CONTRACTOR SHALL CONTINUE TO BE RESPONSIBLE FOR
<br />KEEPING THE TREES PLUMB THROUGHOUT THE GUARANTEE PERIOD.
<br />23. ANY PLANT MATERIAL WHICH DIES, TURNS BROWN, OR DEFOLIATES (PRIOR TO TOTAL
<br />ACCEPTANCE OF THE WORK) SHALL BE PROMPTLY REMOVED FROM THE SITE AND REPLACED WITH
<br />MATERIAL OF THE SAME SPECIES, QUANTITY, AND SIZE AND MEETING ALL LANDSCAPE LEGEND
<br />SPECIFICATIONS.
<br />24. WATERING: MAINTAIN A WATERING SCHEDULE WHICH WILL THOROUGHLY WATER ALL PLANTS
<br />ONCE A WEEK. IN EXTREMELY HOT, DRY WEATHER, WATER MORE OFTEN AS REQUIRED BY
<br />INDICATIONS OF HEAT STRESS SUCH AS WILTING LEAVES. CHECK MOISTURE UNDER MULCH PRIOR
<br />TO WATERING TO DETERMINE NEED. CONTRACTOR SHALL MAKE THE NECESSARY
<br />ARRANGEMENTS FOR WATER.
<br />TURF NOTES:
<br />TURF ESTABLISHMENT SHALL BE ACCOMPLISHED IN ACCORDANCE WITH THE PROVISIONS
<br />OF THE MN/DOT 2105 AND 2575 EXCEPT AS MODIFIED BELOW:
<br />1. ALL AREAS TO RECEIVE SOD SHALL ALSO RECEIVE 4" OF TOPSOIL PRIOR TO
<br />INSTALLING SOD. TOPSOIL SHALL BE FREE OF TREE ROOTS, STUMPS, BUILDING MATERIAL,
<br />AND TRASH, AND SHALL BE FREE OF STONES LARGER THAN 1 2" INCHES IN ANY DIMENSION.
<br />2. WHERE SOD ABUTS PAVED SURFACES, FINISHED GRADE OF SOD/SEED SHALL BE HELD 1" BELOW
<br />SURFACE ELEVATION OF TRAIL, SLAB, CURB, ETC.
<br />3. SOD SHALL BE LAID PARALLEL TO THE CONTOURS AND SHALL HAVE STAGGERED JOINTS. ON
<br />SLOPES STEEPER THAN 3:1 OR IN DRAINAGE SWALES, SOD SHALL BE STAKED SECURELY.
<br />4. TURF ON ALL OTHER AREAS DISTURBED BY CONSTRUCTION SHALL BE RESTORED BY SEEDING,
<br />MULCHING AND FERTILIZING. SEED MIXTURE NO.25-151 WILL BE PLACED AT THE RATE OF 120
<br />POUNDS PER ACRE.
<br />5. ALL DISTURBED AREAS TO BE TURF SEEDED, ARE TO RECEIVE 4" TOP SOIL, SEED, MULCH, AND
<br />WATER UNTIL A HEALTHY STAND OF GRASS IS OBTAINED. FOR SLOPES STEEPER THAN 3:1 OR IN
<br />DRAINAGE SWALES INSTALL EROSION CONTROL BLANKET.
<br />6. ALL DISTURBED AREAS TO RECEIVE NATIVE SEED, ARE TO RECEIVE PLANTING SOIL, SEED, MULCH,
<br />AND WATER UNTIL A HEALTHY STAND OF GRASS IS OBTAINED. FOR SLOPES STEEPER THAN 3:1 OR
<br />IN DRAINAGE SWALES INSTALL EROSION CONTROL BLANKET.
<br />GENERAL TREE SPECIFICATIONS:
<br />1. ALL STREET AND PARKING LOT TREES SHALL BE LIMBED UP TO THE FOLLOWING HEIGHTS:
<br />1.1. 2" CAL. TREES: LOWEST BRANCH 6' HT.
<br />1.2. 3" CAL.+TREES: LOWEST BRANCH 7' HT.
<br />2. TREE CANOPY WIDTH SHALL BE RELATIVE TO HEIGHT/CALIPER OF TREE AND TYPE OF TREE.
<br />2.1. 1" CALIPER/6-8' HT: 3-4' WIDTH MIN.
<br />2.2. 2" CALIPER/12-14' HT: 4-5' WIDTH MIN.
<br />2.3. 3" CALIPER/14-16' HT: 6-7' WIDTH MIN.
<br />3. CANOPY TREES SHALL NOT HAVE CO -DOMINATE LEADERS IN LOWER HALF OF TREE CROWN.
<br />4. ALL TREES SHALL HAVE SYMMETRICAL OR BALANCED BRANCHING ON ALL SIDES OF THE TREE.
<br />5. TREES SHALL NOT BE TIPPED PRUNED.
<br />6. TREES SHALL BE FREE OF PHYSICAL DAMAGE FROM SHIPPING AND HANDLING. DAMAGED TREES
<br />SHALL BE REJECTED.
<br />7. SUMMER DUG TREES SHALL HAVE ROOTBALL SIZE INCREASED BY 20%
<br />8. TREES WHICH EXCEED RECOMMENDED CALIPER TO HEIGHT RELATIONSHIP SHALL BE REJECTED.
<br />IRRIGATION NOTES:
<br />1. IRRIGATION SYSTEM TO BE DESIGN/BUILD. CONTRACTOR TO SUBMIT SHOP DRAWINGS FOR
<br />APPROVAL OF SYSTEM LAYOUT PRIOR TO INSTALLATION.
<br />2. ALL SOD TO RECEIVE SPRAY OR ROTOR IRRIGATION HEADS WITH MINIMUM DESIGN OF 1"
<br />IRRIGATION PER WEEK.
<br />3. ALL PLANT BEDS TO RECEIVE DRIP LINE IRRIGATION, WITH A MINIMUM DESIGN OF .25"
<br />IRRIGATION PER WEEK.
<br />4. CONTRACTOR TO INSTALL A TOTAL OF 4 QUICK COUPLERS AT THE CORNERS OF THE PROPERTY.
<br />A 2.5" TYPE K SOURCE PIPE IS PROVIDED BY MECHANICAL.
<br />Wsambatek
<br />www.sambatek.com
<br />12800 Whitewater Drive, Suite 300
<br />Minnetonka, MN 55343
<br />763.476.6010 telephone
<br />763.476.8532 facsimile
<br />Engineering I Surveying I Planning I Environmental
<br />Client
<br />LA MACCHIA
<br />GROUP
<br />157 NORTH MILWAUKEE STREET,
<br />MILWAUKEE, WI 53202
<br />Project
<br />HEARTLAND
<br />CREDIT UNION
<br />Location
<br />HUGO, MN
<br />Certification
<br />I hereby certify that this plan, specification or
<br />report was prepared by me or under my direct
<br />supervision and that I am a duly licensed
<br />professional ENGINEER under the laws of the state
<br />of Minnesota.
<br />BRADY D. BUSSELMAN
<br />Registration No. 44579 Date: 09/27/2019
<br />If applicable, contact us for a wet signed copy of this
<br />plan which is available upon request at Sambatek's,
<br />Minnetonka, MN office.
<br />Summary
<br />Designed: Drawn: JRW
<br />Approved: Book / Page:
<br />Phase: PRELIMINARY Initial Issued: 09/27/2019
<br />Revision History
<br />No. Date By Submittal / Revision
<br />Sheet Title
<br />LANDSCAPE
<br />DETAILS AND
<br />NOTES
<br />Sheet No. Revision
<br />L1.02
<br />Project No. 21797
<br />
|