Washington
<br />:^=County
<br />Road and Bridge Projects
<br />Local Option - Transportation Sales, Use and Excise Tax - Proposed Projects*
<br />updated - 02/02/2020
<br />Road
<br />From
<br />To
<br />Proposed Work
<br />Length
<br />Cost
<br />Notes
<br />CSAH 15
<br />CSAH 5
<br />TH 36
<br />New Roadway Alignment
<br />0.70
<br />$ 10,950,000
<br />Current CIP - Not fully funded
<br />CR 50
<br />TH 61
<br />CSAH 15
<br />Major Pavement Rehabilitation
<br />6.04
<br />$ 500,000
<br />Not in CIP
<br />CR 57
<br />CSAH 7
<br />CSAH 4
<br />Major Pavement Rehabilitation
<br />7.00
<br />$ 3,500,000
<br />Not in CIP
<br />CR 65
<br />CSAH 10
<br />CSAH 14
<br />Road Reconstruct
<br />3.01
<br />$ 9,350,000
<br />Not in CIP
<br />CSAH 13
<br />CSAH 6
<br />CSAH 14
<br />Road Reconstruct
<br />0.43
<br />$ 4,650,000
<br />Current CIP
<br />CSAH 15
<br />CSAH 7
<br />Lynch Rd
<br />Major Pavement Rehabilitation
<br />0.47
<br />$ 1,800,000
<br />Not in CIP
<br />CSAH 15
<br />62nd St
<br />Intersection Improvement
<br />0.25
<br />$ 500,000
<br />Not in CIP
<br />CSAH 15
<br />CSAH 10
<br />CSAH 14
<br />Road Expansion
<br />3.21
<br />$ 13,950,000
<br />Current CIP - 2022 Bond Project
<br />CSAH 15
<br />TH 36
<br />Interchange
<br />1.00
<br />$ 3,000,000
<br />Current CIP - Not fully funded
<br />CSAH 19
<br />Indian St.
<br />Intersection Improvement
<br />0.25
<br />$ 750,000
<br />Not in CIP
<br />CSAH 24
<br />Oren
<br />59th
<br />New Roadway Alignment
<br />0.17
<br />$ 500,000
<br />Current CIP - Not fully funded
<br />CSAH 18
<br />CSAH 13
<br />Woodlane Drive
<br />Road Expansion
<br />1.00
<br />$ 10,500,000
<br />Current CIP - Not fully funded
<br />CSAH 3
<br />170th
<br />240th
<br />Major Pavement Rehabilitation
<br />7.44
<br />$ 4,200,000
<br />Current CIP - Not fully funded
<br />South Highway Maintenance Facility
<br />New Transportation Facility
<br />NA
<br />$ 15,000,000
<br />Current CIP - 2022 Bond Project
<br />TOTALS: 30.97 $ 79,150,000
<br />*Project list does not represent project construction order or priority
<br />*List may change subject to Board action, matching fund availability (CSAH, Federal, City, Wheelage, etc) or other reasons
<br />Transit Projects
<br />Project
<br />Annual Operating
<br />cost
<br />Capital Cost
<br />Notes
<br />Gold Line Bus Rapid Transit
<br />$ 5,000,000
<br />$ 115,000,000
<br />Capital 2017, Operating 2024
<br />Red Rock Corridor Bus Rapid Transit
<br />$ 8,000,000
<br />$ 44,000,000
<br />Capital TBD, Operating TBD
<br />Rush Line Bus Rapid Transit Extension
<br />TBD
<br />TBD
<br />TBD
<br />Highway 36 Transitway
<br />TBD
<br />TBD
<br />TBD
<br />Forest Lake Transit Station
<br />$ 60,000
<br />N/A
<br />Newport Transit Station
<br />$ 60,000
<br />N/A
<br />( TOTALS:1 $ 13,120,000 15 159,000,000 ii
<br />*Project list does not represent project construction order or priority
<br />*List may change subject to Board action, matching fund availability (CSAH, Federal, City, Wheelage, etc) or other reasons