HomeMy WebLinkAbout2015.09.21.CC PowerPoint Rail updateUpdate on Railroad Spur
September 21, 2015
uty of
I sH
go
Background
Council discussed rail spur during winter of 2014
Discussed usage of spur
Impacts of noise, loading practices
Low volume on Hugo spur
Schwieters
Loadmaster
NRI
Mn Commercial intention to terminate service
Impacts to businesses
MHu`g o
Support from Hugo CC
Railroad succeeded in receiving $145,000
from State of MN
Part of Transportation Bill
Emergency repairs
Patch for one year
Repairs are nearly complete
Approximately $1.1 million still needed for
permanent repairs
"Ii Huty o
2016 legislative session
Bonding proposals being submitted now
Leg. Committees to tour sites this fall
Bonding request
General Fund request
Minnesota Freight Railroad Preservation and
Infrastructure Improvement Act
Citgo
IsiH
Statewide significance
Short -line railroads
Deteriorating infrastructure
Abandonment is occurring
Businesses are dependent on the service
State funds all other types of infrastructure
Including trails
Surrounding states provide financial support
MHu`g o
MFRPII Act
Grant program
New siding, spur, trackage construction
Track improvements, upgrading, maintenance
Repair and replacement of bridges, culverts,
and other important infrastructure
Local Rail Services Assistance Program
Loan program
Existing program has limitations
Requires collateral for loans
MHu`g o
Significance to Hugo
Part of BEIP
TIF District
Rail spur created with CSAH 8 realignment
Available for other Hugo Businesses
Rail service led to investment in BEIP
Economic Development / Jobs
Risk of abandonment
Possible (likely?) loss of businesses /jobs
Future investment and economic expansion
Benefits to Hugo citizens
IMHUg
Council Discussion
Continued support
Legislature's assistance in providing
$1.1 million in grants for permanent repairs
9!6
Railroad
Hugo Line
10 mile line extending southward
3 businesses use the line
Schwieters
Loadmaster Lubricants
NRI
All shipping occurs at the northern terminus
of the Hugo Line
y
INHUgo
Railroad
Part of BEIP
TIF District
Hugo service
Rail spur created with CSAH 8 realignment
Economic Development / Jobs
Rail volumes are lower than original projections
NorLakes (Loadmaster) shipping of grease
Schwieters —shipping of lumber
Impacts of North Dakota oil boom
84 Lumber
Lack of other users
Recession
City 11HU go
Uncertain Future
Hugo Line needs maintenance
Deferred maintenance
Low-cost, stop -gap measures
Low -speed 10mph trains
Significant capital project needed to upgrade
line and maintain service
Strict Federal safety standards
Mi u`go
Status
Mayor Weidt, Council Member Petryk met
with MN Commercial, BNSF, WCRRA, &
businesses
MN Commercial —
Intends to discontinue rail service
Low volume = low revenues
Safety improvements = high costs
Process to begin with STB in April
11HU o
Businesses
Schwieters, Loadmaster load directly into
their yard / building
Rail service is critical to their business
Alternate rail sites, trucking, not feasible
Increased truck traffic
NRI trans -loads scrap remotely at the spur
Alternate sites are available
NRI prefers Hugo site
Spur would need improvements
City 11HU go
What's next
Short time -frame
Additional meetings with businesses
RR needs commitments
"Take or pay" contracts
Financing for capital improvements on rail line
Owned by BNS F
Improvements to spur to lessen impacts
Discussion with WCRRA, State & Feds
Grants, loan programs
Additional shippers on rail line ,siHu`go
What if the rail goes away?
Discontinuance of service
summertime
Reversion to BNSF
Abandonment process is lengthy
Rail would remain for at least two years
Abandonment might sound good to some...
Rush Line Corridor — future transit line
Trail advocates
Nearby neighbors
IMHUg
What if the rail stays?
Who are the users?
Users may need to make long-term
commitments
Are improvements necessary to the spur?
Depends on the users
Are there additional users to lessen burden?
INHU o
Discussion / Direction
Not a decision for the city
Difficult business decisions lie ahead
For Railroad and Rail users
City support of impacted businesses...
Facilitate meetings
Contacts with agencies
Develop a plan / strategy to keep rail service
Assistance finding grants
Economic Development
Find new rail users
Direction to staff
IMHUg